State Plan 2024-25- WSS to Thalassery, Mahe and Dharmadam-summer pumping station at Veliyambra- supplying and fitting 280KW 3.3KV FCMA soft starter for No.1 pump set.
State Plan 2024-25- WSS to Thalassery, Mahe and Dharmadam-summer pumping station at Veliyambra- supplying and fitting 280KW 3.3KV FCMA soft starter for No.1 pump set.
Project Code
KNRGOK082416497
Type
Main project
Funding Agency
GOK
Category
State plan
Type of scheme
Water Supply
Scheme
4215-01-800-89
Description
WSS to Thalassery, Mahe and Dharmadam-summer pumping station at Veliyambra- supplying and fitting 280KW 3.3KV FCMA soft starter for No.1 pump set.
Status
On-going
District
Kannur
Executing Office
Keezhallur PH Sn
AS Amount (Rs)
1420000
AS Number
PIU1/SP/33/2024-25
TS Amount (Rs)
TS Number
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date
Date is not specified
Coverage
Packages
No.
Project Name
Location
View
1
State Plan 2024-25- WSS to Thalassery, Mahe and Dharmadam-summer pumping station at Veliyambra- supplying and fitting 280KW 3.3KV FCMA soft starter for No.1 pump set.
Keezhallur PH Sn
Overall Project Status
Status Date
Overall Project Status
Project Officer
Contact
27 Jun 2025
work completed.trail running in progress
Keezhallur PH Sn AE
17 Jun 2025
Supply of the starter completed and installation to be done.
Keezhallur PH Sn AE
12 Jun 2025
Supply of the starter completed and installation to be done
Keezhallur PH Sn AE
31 May 2025
Supply of the starter completed and installation to be done