Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

MLA-SDF-Kalpetta LA Constituency -Urban Water Supply Scheme to Kalpetta Municipality-Supplying and Erection stand bye 120HP C/F Pumb Set at Goodalai Booster Station.

Project MLA-SDF-Kalpetta LA Constituency -Urban Water Supply Scheme to Kalpetta Municipality-Supplying and Erection stand bye 120HP C/F Pumb Set at Goodalai Booster Station.
Project Code WYDDC-LAC/ADS/SDF/KSCADC02229636
Type Main project
Funding Agency DC-LAC/ADS/SDF/KSCADC
Category MLA SDF
Type of scheme Water Supply
Scheme DC-LAC/ADS/SDF/KSCADC
Description MLA-SDF-Kalpetta LA Constituency -Urban Water Supply Scheme to Kalpetta Municipality-Supplying and Erection stand bye 120HP C/F Pumb Set at Goodalai Booster Station.
Status Completed
District Wayanad
Executing Office Kalpetta PH Sub Dn
AS Amount (Rs) 2250000
AS Number R.D.3/343/2022
TS Amount (Rs) 2250000
TS Number TS/2021-2022/2021/42849
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 500
Capacity in MLD 10.00
Actual Project Completion Date Date is not specified
Coverage Kalpetta Municipality
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 MLA-SDF-Kalpetta LA Constituency -Urban Water Supply Scheme to Kalpetta Municipality-Supplying and Erection stand bye 120HP C/F Pumb Set at Goodalai Booster Station. Kalpetta PH Sn 1

Overall Project Status

Status Date Overall Project Status Project Officer Contact
25 May 2023 BILL SUBMITTED TO DIVISION OFFICE Kalpetta PH Sn 1 - AE
22 May 2023 bill submitted to subdivision office Kalpetta PH Sn 1 - AE
18 May 2023 bill submitted to subdivision office Kalpetta PH Sn 1 - AE
15 May 2023 bill submitted to subdivision office Kalpetta PH Sn 1 - AE
09 May 2023 work completed bill under preparation Kalpetta PH Sn 1 - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 03/02/2022
Scheduled date of Completion of the Project 30 Sep 2022
Expected date of Completion 30/09/2022

Processing Dates

AS Date 03 Feb 2022
TS Date 08 Feb 2022

Other details

Project Officers View