- Home
- Plan-30-2017-18-TSS- E Block Zone II - L...
Plan-30-2017-18-TSS- E Block Zone II - Laying 700mm dia RCC NP3 pipe sewer main from Jagathy towards common manhole ch 512m to 785m
| Project |
Plan-30-2017-18-TSS- E Block Zone II - Laying 700mm dia RCC NP3 pipe sewer main from Jagathy towards common manhole ch 512m to 785m |
| Project Code |
TVMGOK10175887 |
| Type |
Main project |
| Category |
State plan |
| Description |
TSS- E Block Zone II - Laying 700mm dia RCC NP3 pipe sewer main from Jagathy towards common manhole ch 512m to 785m |
| District |
Thiruvananthapuram |
| Execution |
Pattoor Sewerage Dn |
| AS Amount (Rs) |
19000000.00 |
| Total Bill Submitted (Rs) |
-- |
| Total Bill Paid (Rs) |
-- |
| Coverage |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 17 May 2021 |
Land Acquisition 19(1) declaration stage final stage work arranged under State plan 20-21 |
Pattoor Sewerage Dn |
|
| 12 May 2021 |
Land Acquisition 19(1) declaration stage final stage work arranged under State plan 20-21 |
Pattoor Sewerage Dn |
|
| 07 May 2021 |
Land Acquisition 19(1) declaration stage final stage work arranged under State plan 20-21 |
Pattoor Sewerage Dn |
|
| 05 May 2021 |
Land Acquisition 19(1) declaration stage final stage work arranged under State plan 20-21 |
Pattoor Sewerage Dn |
|
| 03 May 2021 |
Land Acquisition 19(1) declaration stage final stage work arranged under State plan 20-21 |
Pattoor Sewerage Dn |
|
No project review have been added to this project
Packages
| No. |
Project Name |
Location |
View |
| 1 |
Plan-30-2017-18-TSS- E Block Zone II - Laying 700mm dia RCC NP3 pipe sewer main from Jagathy towards common manhole ch 512m to 785m Project Code TVMGOK10175887 |
Pattoor Sewerage Dn |
|
Duration & Sanction dates
| Date of Sanction |
05/10/2017 |
| Date of start |
Date is not specified |
| Expected date of Completion |
31/12/2021 |
Other details
| Project Officers |
View |
| Funding Agency |
GOK |