DEPOSIT WORK-2022-23 -RWSS to Adat - Laying additional branched pumping main (Hot Line ) from Puzhakkal pumphouse to over head tanks at Chakkyaparambu in Adat Panchayat Zone 2

Project DEPOSIT WORK-2022-23 -RWSS to Adat - Laying additional branched pumping main (Hot Line ) from Puzhakkal pumphouse to over head tanks at Chakkyaparambu in Adat Panchayat Zone 2
Project Code TCRDEPO102011899
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit work-RWSS to Adat - Laying additional branched pumping main (Hot Line ) from Puzhakkal pumphouse to over head tanks at Chakkyaparambu in Adat Panchayat Zone 2
Status Completed
District Thrissur
Executing Office Thrissur WW Sn 2
AS Amount (Rs) 4800000
AS Number A-127/20-21 dtd 14/09/2020
TS Amount (Rs) 4800000
TS Number TS/2022-2023/2018/15097
Total Bill Submitted (Rs) 1
Total Bill Paid (Rs) 1
Population Benefitted 1000
Capacity in MLD 0.04
Actual Project Completion Date 25 Nov 2022
Coverage Chakkyamparambu Area Adat
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 DEPOSIT WORK-2022-23 -RWSS to Adat - Laying additional branched pumping main (Hot Line ) from Puzhakkal pumphouse to over head tanks at Chakkyaparambu in Adat Panchayat Zone 2 Thrissur WW Sn 2

Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Aug 2023 Work Completed- Bill paid ( UC fwd) Thrissur PH Dn EE
10 May 2023 Completed-Bill submitted. Thrissur PH Dn EE
10 Feb 2023 work completed. Bill under preparation. Thrissur PH Dn EE
10 Feb 2023 Pipeline laying work is completed, Airvalve fixing 8 Nos completed. Thrissur WW Sn - AE 2
09 Feb 2023 Pipeline laying work is completed, Airvalve fixing 8 Nos completed. Thrissur WW Sn - AE 2

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 20/10/2022
Scheduled date of Completion of the Project 25 Nov 2022
Expected date of Completion 31/08/2023

Processing Dates

AS Date 01 Oct 2020
TS Date 15 Jul 2022

Other details

Project Officers View