Rebuild Kerala:Automation of submersible pumps in Kerala water authority-Implementation of phase-I(stage I &II) part under rebuild Kerala initiative -post supportive activities-Disinfection arrangements- RWSS to Mynagappally & Westkallada.

Project Rebuild Kerala:Automation of submersible pumps in Kerala water authority-Implementation of phase-I(stage I &II) part under rebuild Kerala initiative -post supportive activities-Disinfection arrangements- RWSS to Mynagappally & Westkallada.
Project Code KLMRKI032215024
Type Main project
Funding Agency RKI
Category RKI
Type of scheme Water Supply
Scheme 5475-00-115-94-05
Description Automation of submersible pumps in Kerala water authority-Implementation of phase-I(stage I &II) part under rebuild Kerala initiative -post supportive activities-Disinfection arrangements- RWSS to Mynagappally & Westkallada.
Status On-going
District Kollam
Executing Office Sasthamcottah WS Sn2
AS Amount (Rs) 1830000
AS Number 6296/AE1(OPERATIONS)/2022/KWA
TS Amount (Rs) 210000
TS Number 9933/2022-2023
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 Rebuild Kerala:Automation of submersible pumps in Kerala water authority-Implementation of phase-I(stage I &II) part under rebuild Kerala initiative -post supportive activities-Disinfection arrangements- RWSS to Mynagappally & Westkallada. Sasthamcottah WS Sn2

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 May 2024 Rebuild Kerala:Automation of submersible pumps in Kerala water authority-Implementation of phase-I(stage I &II) part under rebuild Kerala initiative -post supportive activities-Disinfection arrangements- RWSS to Mynagappally & Westkallada. Sasthamcotta WS Sn 2 HW - AE
09 May 2024 Work was tendered two more times ,but no offers were received.Hence the estimate was revised & submitted for revised AS on 2022.Work was tendered two more times ,but no offers were received.Hence the estimate was revised & submitted for revised AS on 2022. Sasthamcotta WS Sn 2 HW - AE
06 May 2024 Work was tendered two more times ,but no offers were received.Hence the estimate was revised & submitted for revised AS on 2022.Work was tendered two more times ,but no offers were received.Hence the estimate was revised & submitted for revised AS on 2022. Sasthamcotta WS Sn 2 HW - AE
03 May 2024 Work was tendered two more times ,but no offers were received.Hence the estimate was revised & submitted for revised AS on 2022.Work was tendered two more times ,but no offers were received.Hence the estimate was revised & submitted for revised AS on 2022. Sasthamcotta WS Sn 2 HW - AE
29 Apr 2024 Work was tendered two more times ,but no offers were received.Hence the estimate was revised & submitted for revised AS on 2022.Work was tendered two more times ,but no offers were received.Hence the estimate was revised & submitted for revised AS on 2022. Sasthamcotta WS Sn 2 HW - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 13/07/2022
Scheduled date of Completion of the Project 20 Jul 2022
Expected date of Completion 20/07/2022

Processing Dates

AS Date 30 Mar 2022
TS Date 13 Jul 2022

Other details

Project Officers View