Jal Jeevan Mission- 21-22- CWSS to Thazhekkode and Alipparamba - Package III - Survey , design , supplying and laying of distribution system to Thazhekkode and Alipparamba Panchayath.
Project |
Jal Jeevan Mission- 21-22- CWSS to Thazhekkode and Alipparamba - Package III - Survey , design , supplying and laying of distribution system to Thazhekkode and Alipparamba Panchayath. |
Project Code |
MLPJJM092110135P3 |
Type |
Package |
Main Project |
Jal Jeevan Mission- 21-22- CWSS to Thazhekkode and Alipparamba Panchayath in Malappuram District
|
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-01 |
Description |
Package III - Survey , design , supplying and laying of distribution system to Thazhekkode and Alipparamba Panchayath and providing FHTCs. |
Status |
On-going |
District |
Malappuram |
Executing Office |
Malappuram Project Dn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
78380 |
TS Number |
15143/21-22 |
Technical specification |
Pipe line extension and providing FHTCs |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
20/05/2022 |
Scheduled date of Completion as per agreement |
15 Sep 2023 |
Expected date of Completion |
31/03/2024 |
Processing Dates
TS Date |
10 Dec 2021 |
Estimate Approval |
10 Dec 2021 |
NIT Approval |
12 Jan 2022 |
Tender Closing |
15 Mar 2022 |
Technichal Pre-Qualification |
22 Mar 2022 |
Price bid opening |
13 Apr 2022 |
Approval Dates
Workorder Date |
09 May 2022 |
NA |
20 May 2022 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Malappuram Project Dn AE2 |
Date: 05/07/2025 |
Work in progress | 92% Completed
work in progress balance interconnection and gap filling work are in progressing.
Malappuram Project Dn EE |
Date: 27/06/2025 |
Work in progress | 90% Completed
Pipeline in Thazhekkode and Alipparamba panchayath progressing-321 km completed . 10350 HTC completed, geotagging work completed. Balance work pending due to getting permission from PWD and NHAI..