Jal Jeevan Mission- 21-22- CWSS to Thazhekkode and Alipparamba - Package III - Survey , design , supplying and laying of distribution system to Thazhekkode and Alipparamba Panchayath.

Project Jal Jeevan Mission- 21-22- CWSS to Thazhekkode and Alipparamba - Package III - Survey , design , supplying and laying of distribution system to Thazhekkode and Alipparamba Panchayath.
Project Code MLPJJM092110135P3
Type Package
Main Project Jal Jeevan Mission- 21-22- CWSS to Thazhekkode and Alipparamba Panchayath in Malappuram District
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Package III - Survey , design , supplying and laying of distribution system to Thazhekkode and Alipparamba Panchayath and providing FHTCs.
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 78380
TS Number 15143/21-22
Technical specification Pipe line extension and providing FHTCs

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 20/05/2022
Scheduled date of Completion as per agreement 15 Sep 2023
Expected date of Completion 31/03/2024

Processing Dates

TS Date 10 Dec 2021
Estimate Approval 10 Dec 2021
NIT Approval 12 Jan 2022
Tender Closing 15 Mar 2022
Technichal Pre-Qualification 22 Mar 2022
Price bid opening 13 Apr 2022

Approval Dates

Workorder Date 09 May 2022
NA 20 May 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Malappuram Project Dn AE2
Date: 05/07/2025

Work in progress | 92% Completed

work in progress balance interconnection and gap filling work are in progressing.

Malappuram Project Dn EE
Date: 27/06/2025

Work in progress | 90% Completed

Pipeline in Thazhekkode and Alipparamba panchayath progressing-321 km completed . 10350 HTC completed, geotagging work completed. Balance work pending due to getting permission from PWD and NHAI..