JJM- KANNUR DISTRICT -THILLANKERY GRAMA PNCHAYATH -WSS TO MATTANNUR , IRITTY AND ADJOINING PANCHAYATH PHASE III- LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs.

Project JJM- KANNUR DISTRICT -THILLANKERY GRAMA PNCHAYATH -WSS TO MATTANNUR , IRITTY AND ADJOINING PANCHAYATH PHASE III- LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs.
Project Code KNRJJM09218679P1
Type Package
Main Project JJM- KANNUR DISTRICT -THILLANKERY GRAMA PNCHAYATH -WSS TO MATTANNUR , IRITTY AND ADJOINING PANCHAYATH PHASE III- LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs.
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Laying Gravity main, Construction of Service reservoirs, Laying pumping main,Laying distribution system and providing FHTCs
Status On-going
District Kannur
Executing Office Mattannur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 242700000
TS Number 18218/2021-2022
Technical specification Laying 250 mm DI K9 gravity main from Naduvanad to GLSR at Kanhirad, Construction of 6 LL GLSR at Kanhirad, 1LL OHSR at Kanhiradmala, Laying 150 mm DI K9 Pumping main from GLSR at Kanhirad to OHSR at Kanhiradmala , Laying distribution system OF 78380 m with 350 mm DI K9 to 90 mm pvc and 140 mm to 90mm HDPE pipes and providing 2909 Nos FHTCs
Contractor VINODAN K (Mob: 9388860500)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 25/06/2022
Scheduled date of Completion as per agreement 24 Mar 2023
Expected date of Completion 30/04/2025

Processing Dates

TS Date 18 Jan 2022
Estimate Approval 18 Jan 2022
NIT Approval 19 Feb 2022
Tender Closing 19 Mar 2022
Technichal Pre-Qualification 19 Feb 2022
Price bid opening 21 Mar 2022

Approval Dates

Workorder Date 25 Jun 2022
NA 30 Jun 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Mattannur Project Sn 2 AE
Date: 12/05/2025

Work in progress | 98% Completed

Pipe layiing of 121 km completed, out of 121.23km of total distribution. Construction of 6LL GLSR at Kanhirad all work completed & 1LL GLSR at Kanhiradmala also completed. 3555nos. HTC completed. Trial running and charging under progress,90 % completed. KSEB power connection is awaiting. An approach of 70m length gap pipe laying is in private land permission issue has resolved. hard rock breaking & removing work completed, pipe laying work in progress. LSGD Road restoration work,10km tarring completed out of 18km..

Mattannur Project Sn 2 AE
Date: 03/05/2025

Work in progress | 98% Completed

Pipe layiing of 121 km completed, out of 121.23km of total distribution. Construction of 6LL GLSR at Kanhirad all work completed & 1LL GLSR at Kanhiradmala also completed. 3555nos. HTC completed. Trial running and charging under progress,90 % completed. KSEB power connection is awaiting. An approach of 70m length gap pipe laying is in private land permission issue has resolved.hard rock breaking & removing work completed,pipe laying work in progress. LSGD ROad restoration work,10km tarring completed out of 18km..