| Project | JJM- KANNUR DISTRICT -THILLANKERY GRAMA PNCHAYATH -WSS TO MATTANNUR , IRITTY AND ADJOINING PANCHAYATH PHASE III- LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs. |
|---|---|
| Project Code | KNRJJM09218679P1 |
| Type | Package |
| Main Project | JJM- KANNUR DISTRICT -THILLANKERY GRAMA PNCHAYATH -WSS TO MATTANNUR , IRITTY AND ADJOINING PANCHAYATH PHASE III- LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs. |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Laying Gravity main, Construction of Service reservoirs, Laying pumping main,Laying distribution system and providing FHTCs |
| Status | On-going |
| District | Kannur |
| Executing Office | Mattannur Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 242700000 |
| TS Number | 18218/2021-2022 |
| Technical specification | Laying 250 mm DI K9 gravity main from Naduvanad to GLSR at Kanhirad, Construction of 6 LL GLSR at Kanhirad, 1LL OHSR at Kanhiradmala, Laying 150 mm DI K9 Pumping main from GLSR at Kanhirad to OHSR at Kanhiradmala , Laying distribution system OF 78380 m with 350 mm DI K9 to 90 mm pvc and 140 mm to 90mm HDPE pipes and providing 2909 Nos FHTCs |
| Contractor | VINODAN K (Mob: 9388860500) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 25/06/2022 |
|---|---|
| Scheduled date of Completion as per agreement | 24 Mar 2023 |
| Expected date of Completion | 30/04/2025 |
| TS Date | 18 Jan 2022 |
|---|---|
| Estimate Approval | 18 Jan 2022 |
| NIT Approval | 19 Feb 2022 |
| Tender Closing | 19 Mar 2022 |
| Technichal Pre-Qualification | 19 Feb 2022 |
| Price bid opening | 21 Mar 2022 |
| Workorder Date | 25 Jun 2022 |
|---|---|
| NA | 30 Jun 2022 |
| Mattannur Project Sn 2 AE |
| Date: 05/01/2026 |
Work in progress | 99% Completed
Pipe layiing of 121.23 km completed, out of 121.23 km total distribution. Construction of 6LL GLSR at Kanhirad all work completed & 1LL GLSR at Kanhiradmala also completed. 3459nos. FHTC new connection completed.Remaining 95 nos. HTC line charging in progress. Trial running, line charging and supply of water under progress,95 % completed. 12HP Pumpset errection & installation work completed. KSEB power connection obtained. Pumping to 1LL GLSR completed,suppply from 1LL GLSR started.Construction of compound wall at 1.0LL GLSR at Kanhiradmala in progress. LSGD Road restoration work,8.5km tarring completed out of 13.5 km..
| Mattannur Project Sn 2 AE |
| Date: 30/12/2025 |
Work in progress | 99% Completed
Pipe layiing of 121.23 km completed, out of 121.23 km total distribution. Construction of 6LL GLSR at Kanhirad all work completed & 1LL GLSR at Kanhiradmala also completed. 3450nos. FHTC new connection completed remaining 102nos. HTC line charging in progress. Trial running, line charging and supply of water under progress,95 % completed. 12HP Pumpset errection & installation work completed. KSEB power connection obtained. Pumping to 1LL GLSR completed,suppply from 1LL GLSR started.Construction of compound wall at 1.0LL GLSR at Kanhiradmala in progress. LSGD Road restoration work,8.5km tarring completed out of 13.5 km..