Project | JJM- KANNUR DISTRICT -THILLANKERY GRAMA PNCHAYATH -WSS TO MATTANNUR , IRITTY AND ADJOINING PANCHAYATH PHASE III- LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs. |
---|---|
Project Code | KNRJJM09218679P1 |
Type | Package |
Main Project | JJM- KANNUR DISTRICT -THILLANKERY GRAMA PNCHAYATH -WSS TO MATTANNUR , IRITTY AND ADJOINING PANCHAYATH PHASE III- LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs. |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-01 |
Description | Laying Gravity main, Construction of Service reservoirs, Laying pumping main,Laying distribution system and providing FHTCs |
Status | On-going |
District | Kannur |
Executing Office | Mattannur Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 242700000 |
TS Number | 18218/2021-2022 |
Technical specification | Laying 250 mm DI K9 gravity main from Naduvanad to GLSR at Kanhirad, Construction of 6 LL GLSR at Kanhirad, 1LL OHSR at Kanhiradmala, Laying 150 mm DI K9 Pumping main from GLSR at Kanhirad to OHSR at Kanhiradmala , Laying distribution system OF 78380 m with 350 mm DI K9 to 90 mm pvc and 140 mm to 90mm HDPE pipes and providing 2909 Nos FHTCs |
Contractor | VINODAN K (Mob: 9388860500) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 25/06/2022 |
---|---|
Scheduled date of Completion as per agreement | 24 Mar 2023 |
Expected date of Completion | 30/04/2025 |
TS Date | 18 Jan 2022 |
---|---|
Estimate Approval | 18 Jan 2022 |
NIT Approval | 19 Feb 2022 |
Tender Closing | 19 Mar 2022 |
Technichal Pre-Qualification | 19 Feb 2022 |
Price bid opening | 21 Mar 2022 |
Workorder Date | 25 Jun 2022 |
---|---|
NA | 30 Jun 2022 |
Mattannur Project Sn 2 AE |
Date: 12/05/2025 |
Work in progress | 98% Completed
Pipe layiing of 121 km completed, out of 121.23km of total distribution. Construction of 6LL GLSR at Kanhirad all work completed & 1LL GLSR at Kanhiradmala also completed. 3555nos. HTC completed. Trial running and charging under progress,90 % completed. KSEB power connection is awaiting. An approach of 70m length gap pipe laying is in private land permission issue has resolved. hard rock breaking & removing work completed, pipe laying work in progress. LSGD Road restoration work,10km tarring completed out of 18km..
Mattannur Project Sn 2 AE |
Date: 03/05/2025 |
Work in progress | 98% Completed
Pipe layiing of 121 km completed, out of 121.23km of total distribution. Construction of 6LL GLSR at Kanhirad all work completed & 1LL GLSR at Kanhiradmala also completed. 3555nos. HTC completed. Trial running and charging under progress,90 % completed. KSEB power connection is awaiting. An approach of 70m length gap pipe laying is in private land permission issue has resolved.hard rock breaking & removing work completed,pipe laying work in progress. LSGD ROad restoration work,10km tarring completed out of 18km..