Jal Jeevan Mission :2020-21: Puramattom Grama Panchayath:- Pipe line Extensionand Providing new FHTC's. in various locations

Project Jal Jeevan Mission :2020-21: Puramattom Grama Panchayath:- Pipe line Extensionand Providing new FHTC's. in various locations
Project Code PTAJJM12207319P1
Type Package
Main Project Jal Jeevan Mission :2020-21: Puramattom Grama Panchayath:- Pipe line Extensionand Providing new FHTC's. in various locations
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Jal Jeevan Mission :2020-21: Puramattom Grama Panchayath:- Pipe line Extensionand Providing new FHTC's. in various locations
Status On-going
District Pathanamthitta
Executing Office Pullad Section
Agreement Number
Agreement Date
TS Amount (Rs) 12580000
TS Number TS/2021-22/2020/15244
Technical specification Pipe line Extensionand Providing new FHTC's. in various locations
Contractor SanilKumar (Mob: 9447234871)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 24/12/2020
Scheduled date of Completion as per agreement 04 Jul 2022
Expected date of Completion 15/10/2022

Processing Dates

TS Date 23 Nov 2021
Estimate Approval 23 Nov 2021
NIT Approval 25 Nov 2021
Tender Closing 13 Dec 2021
Technichal Pre-Qualification 15 Dec 2021
Price bid opening 15 Dec 2021

Approval Dates

Workorder Date 29 Dec 2021
NA 05 Jan 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Pullad PH Sn - AE
Date: 30/06/2023

Work in progress | 99% Completed

99 % of Work Completed.

Pullad PH Sn - AE
Date: 26/06/2023

Work in progress | 99% Completed

99 % of Work Completed. Erection of pumpset work Pending..