| Project | Jal Jeevan Mission :2020-21: Puramattom Grama Panchayath:- Pipe line Extensionand Providing new FHTC's. in various locations |
|---|---|
| Project Code | PTAJJM12207319P1 |
| Type | Package |
| Main Project | Jal Jeevan Mission :2020-21: Puramattom Grama Panchayath:- Pipe line Extensionand Providing new FHTC's. in various locations |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Jal Jeevan Mission :2020-21: Puramattom Grama Panchayath:- Pipe line Extensionand Providing new FHTC's. in various locations |
| Status | On-going |
| District | Pathanamthitta |
| Executing Office | Pullad Section |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 12580000 |
| TS Number | TS/2021-22/2020/15244 |
| Technical specification | Pipe line Extensionand Providing new FHTC's. in various locations |
| Contractor | SanilKumar (Mob: 9447234871) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 24/12/2020 |
|---|---|
| Scheduled date of Completion as per agreement | 04 Jul 2022 |
| Expected date of Completion | 15/10/2022 |
| TS Date | 23 Nov 2021 |
|---|---|
| Estimate Approval | 23 Nov 2021 |
| NIT Approval | 25 Nov 2021 |
| Tender Closing | 13 Dec 2021 |
| Technichal Pre-Qualification | 15 Dec 2021 |
| Price bid opening | 15 Dec 2021 |
| Workorder Date | 29 Dec 2021 |
|---|---|
| NA | 05 Jan 2022 |
| Pullad PH Sn - AE |
| Date: 30/06/2023 |
Work in progress | 99% Completed
99 % of Work Completed.
| Pullad PH Sn - AE |
| Date: 26/06/2023 |
Work in progress | 99% Completed
99 % of Work Completed. Erection of pumpset work Pending..