Project | RKI-Automation of Vertical Turbine pumpsets in KWA- Phase 1- Stage 2- CARWSS to Thirunavaya & adj pyths |
---|---|
Project Code | MLPRKI042212024P5 |
Type | Package |
Main Project | RKI-Automation of Vertical Turbine pumpsets in KWA- Phase 1- Stage 2 |
Funding Agency | RKI |
Category | RKI |
Type of scheme | Water Supply |
Scheme | 5475-00-115-94-05 |
Description | RKI-Automation of Vertical Turbine pumpsets in KWA- Phase 1- Stage 2- CARWSS to Thirunavaya & adj pyths |
Status | Completed |
District | Malappuram |
Executing Office | Kottakkal PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | |
TS Number | |
Technical specification | Automation VT pump |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | Date is not specified |
---|---|
Scheduled date of Completion as per agreement | 24 Dec 2022 |
Expected date of Completion | Date is not specified |
Workorder Date | 09 Nov 2022 |
---|---|
NA | 25 Nov 2022 |
Tirur Sn AE |
Date: 01/04/2023 |
Work has been completed | 100% Completed
work completed.
Kottakkal PH Sn AE |
Date: 02/09/2022 |
Work has started | 0% Completed
Not under this section.