Jal Jeevan Mission-Kasaragod District-East Eleri Panchayat-WSS to East Eleri Phase II

Project Jal Jeevan Mission-Kasaragod District-East Eleri Panchayat-WSS to East Eleri Phase II
Project Code KGDJJM08203010
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Laying distribution network and providing FHTCs Distribution network - 110 mm pvc 10 kg - 1000 m, 90 pvc 10 kg - 500 m, 63 pvc 10 kg - 1500 m, 50 pvc 10 kg - 8000 m, 50 pvc 12.5 kg - 1500 m, 63 pvc 12.5 kg - 500 m, 90 pvc 12.5 kg - 1000m, 110 pvc 12.5 kg - 2000 m, 140 pvc 12.5 kg - 1000 m, 160 pvc 12.5 kg - 500 m, FHTC s- 3708 nos.
Status On-going
District Kasaragod
Executing Office Kanhangad Project Division
AS Amount (Rs) 91800000
AS Number GO.(RT)No.541/2020WRD
TS Amount (Rs) 23800000
TS Number 11457/2020-21
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted 25075
Capacity in MLD 3.00
Actual Project Completion Date 28 Feb 2022
Coverage East Eleri Panchayat
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal jeevan mission- East Eleri Panchayat- Kasaragod District- Water Supply Scheme to East Eleri Pachayat- Phase II- Zone I (Palavayal,Nallompuza,Kamballur part and adjoining areas) Project Division Kannur ( KGD)
2 Jal jeevan mission- Kasaragod District - East Eleri Panchayat- - Water Supply Scheme to East Eleri Phase II- Zone II (Kundaram,Chvaragiri,Thayyeni,Kamballur part and adjoining areas) Project Division Kannur ( KGD)

Overall Project Status

Status Date Overall Project Status Project Officer Contact
15 May 2024 Work in progress Kanhangad Proj Dn AE - 2
09 May 2024 Work in progress Kanhangad Proj Dn AE - 2
03 Apr 2024 Work in progress Kanhangad Proj Dn AE - 2
04 Mar 2024 Work in progress Kanhangad Proj Dn AE - 2
27 Feb 2024 Work in progress Kanhangad Proj Dn AEE - 1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 11/08/2021
Scheduled date of Completion of the Project 21 Nov 2021
Expected date of Completion 31/03/2022

Processing Dates

AS Date 21 Aug 2020
TS Date 27 Aug 2020

Other details

Project Officers View