JICA-JJM IEC Activities -JJM slogan/ picture painting -Repainting of Pump houses / office buildings , Quarters etc -JICA Assisted WSS to Pattuvam and Adjoining Villages- Intake Well cum Pump house at Kuyiloor-General Civil Work

Project JICA-JJM IEC Activities -JJM slogan/ picture painting -Repainting of Pump houses / office buildings , Quarters etc -JICA Assisted WSS to Pattuvam and Adjoining Villages- Intake Well cum Pump house at Kuyiloor-General Civil Work
Project Code KNRJJM082015838P2
Type Package
Main Project (1) JICA-JJM IEC Activities -JJM slogan/ picture painting -Repainting of Pump houses / office buildings , Quarters etc -Repainting of WTP-General Civil Work , (2) JICA-JJM IEC Activities -JJM slogan/ picture painting -Repainting of Pump houses / office buildings , Quarters etc -JICA Assisted WSS to Pattuvam and Adjoining Villages- Intake Well cum Pump house at Kuyiloor-General Civil Work
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description JICA-JJM IEC Activities -JJM slogan/ picture painting -Repainting of Pump houses / office buildings , Quarters etc -JICA Assisted WSS to Pattuvam and Adjoining Villages- Intake Well cum Pump house at Kuyiloor-General Civil Work
Status On-going
District Kannur
Executing Office Irikkur HW Sn
Agreement Number
Agreement Date
TS Amount (Rs) 1126666
TS Number 28717/2023-2024
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 07/06/2024
Scheduled date of Completion as per agreement 06 Aug 2024
Expected date of Completion Date is not specified

Processing Dates

TS Date 29 Feb 2024
Estimate Approval 27 Feb 2024

Approval Dates

Workorder Date 15 Mar 2024
NA 28 May 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Thaliparamba WS Dn EE
Date: 04/06/2025

Work has been completed | 100% Completed

WORK COMPLETED AND BILL SUBMITTED .

Thaliparamba WS Dn EE
Date: 03/06/2025

Work has been completed | 100% Completed

WORK COMPLETED AND BILL SUBMITTED .