JJM-2020-21- Cherukole Grama Panchaayth-Providing Functional Household Tap Connections in Cherukole Grama Panchayath(Phase-II)
Project |
JJM-2020-21- Cherukole Grama Panchaayth-Providing Functional Household Tap Connections in Cherukole Grama Panchayath(Phase-II) |
Project Code |
PTAJJM12209026 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM-2020-21- Cherukole Grama Panchaayth-Providing Functional Household Tap Connections in Cherukole Grama Panchayath(Phase-II) |
Status |
Completed |
District |
Pathanamthitta |
Executing Office |
Pathanamthitta PH Circle |
AS Amount (Rs) |
329600000
|
AS Number |
GO(Rt)No.777/2020/WRD |
TS Amount (Rs) |
12500000 |
TS Number |
TS/2021-2022/2021/35634 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
3000 |
Capacity in MLD |
0.25 |
Actual Project Completion Date |
31 May 2022 |
Coverage |
Cherukole |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM-2020-21- Cherukole Grama Panchaayth-Providing Functional Household Tap Connections in Cherukole Grama Panchayath(Phase-II) |
Ranni Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
17 Jan 2024 |
work completed |
Ranni PH Sn - AE |
|
03 Jan 2024 |
304 nos FHTCs given, and bill submitted for 304 Nos FHTcs. . Pipe laying completed. Only interconnection works are pending due to delay in getting road cutting sanction. Actual time of completion of work was 28.06.2022 ,Contractor submitted time of extension application up to 27.09.2022 and the same attached here with |
Ranni PH Sn - AE |
|
01 Jan 2024 |
304 nos FHTCs given, and bill submitted for 304 Nos FHTcs. . Pipe laying completed. Only interconnection works are pending due to delay in getting road cutting sanction. Actual time of completion of work was 28.06.2022 ,Contractor submitted time of extension application up to 27.09.2022 and the same attached here with |
Ranni PH Sn - AE |
|
30 Dec 2023 |
304 nos FHTCs given, and bill submitted for 304 Nos FHTcs. . Pipe laying completed. Only interconnection works are pending due to delay in getting road cutting sanction. Actual time of completion of work was 28.06.2022 ,Contractor submitted time of extension application up to 27.09.2022 and the same attached here with. |
Ranni PH Sn - AE |
|
29 Dec 2023 |
304 nos FHTCs given, and bill submitted for 304 Nos FHTcs. . Pipe laying completed. Only interconnection works are pending due to delay in getting road cutting sanction. Actual time of completion of work was 28.06.2022 ,Contractor submitted time of extension application up to 27.09.2022 and the same attached here with. |
Ranni PH Sn - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
10/02/2022 |
Scheduled date of Completion of the Project |
28 Jun 2022 |
Expected date of Completion |
30/09/2022 |
Processing Dates
AS Date |
24 Dec 2020 |
TS Date |
30 Nov 2021 |