JJM-2020-21- Cherukole Grama Panchaayth-Providing Functional Household Tap Connections in Cherukole Grama Panchayath(Phase-II)

Project JJM-2020-21- Cherukole Grama Panchaayth-Providing Functional Household Tap Connections in Cherukole Grama Panchayath(Phase-II)
Project Code PTAJJM12209026
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM-2020-21- Cherukole Grama Panchaayth-Providing Functional Household Tap Connections in Cherukole Grama Panchayath(Phase-II)
Status Completed
District Pathanamthitta
Executing Office Pathanamthitta PH Circle
AS Amount (Rs) 329600000
AS Number GO(Rt)No.777/2020/WRD
TS Amount (Rs) 12500000
TS Number TS/2021-2022/2021/35634
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 3000
Capacity in MLD 0.25
Actual Project Completion Date 31 May 2022
Coverage Cherukole
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM-2020-21- Cherukole Grama Panchaayth-Providing Functional Household Tap Connections in Cherukole Grama Panchayath(Phase-II) Ranni Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 Jan 2024 work completed Ranni PH Sn - AE
03 Jan 2024 304 nos FHTCs given, and bill submitted for 304 Nos FHTcs. . Pipe laying completed. Only interconnection works are pending due to delay in getting road cutting sanction. Actual time of completion of work was 28.06.2022 ,Contractor submitted time of extension application up to 27.09.2022 and the same attached here with Ranni PH Sn - AE
01 Jan 2024 304 nos FHTCs given, and bill submitted for 304 Nos FHTcs. . Pipe laying completed. Only interconnection works are pending due to delay in getting road cutting sanction. Actual time of completion of work was 28.06.2022 ,Contractor submitted time of extension application up to 27.09.2022 and the same attached here with Ranni PH Sn - AE
30 Dec 2023 304 nos FHTCs given, and bill submitted for 304 Nos FHTcs. . Pipe laying completed. Only interconnection works are pending due to delay in getting road cutting sanction. Actual time of completion of work was 28.06.2022 ,Contractor submitted time of extension application up to 27.09.2022 and the same attached here with. Ranni PH Sn - AE
29 Dec 2023 304 nos FHTCs given, and bill submitted for 304 Nos FHTcs. . Pipe laying completed. Only interconnection works are pending due to delay in getting road cutting sanction. Actual time of completion of work was 28.06.2022 ,Contractor submitted time of extension application up to 27.09.2022 and the same attached here with. Ranni PH Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 10/02/2022
Scheduled date of Completion of the Project 28 Jun 2022
Expected date of Completion 30/09/2022

Processing Dates

AS Date 24 Dec 2020
TS Date 30 Nov 2021

Other details