DEPOSIT-ARWSS to Keerampara-Replacing damaged GI pipes-ARWSS to Keerampara-Replacing damaged GI pipes at Oojappara due to road widening in Keerampara Panchayath-Pipeline Work

Project DEPOSIT-ARWSS to Keerampara-Replacing damaged GI pipes-ARWSS to Keerampara-Replacing damaged GI pipes at Oojappara due to road widening in Keerampara Panchayath-Pipeline Work
Project Code EKMDEPO032114785
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-ARWSS to Keerampara-Replacing damaged GI pipes-ARWSS to Keerampara-Replacing damaged GI pipes at Oonjappara due to road widening in Keerampara Panchayath-Pipeline Work
Status Completed
District Ernakulam
Executing Office Muvattupuzha PH Dn
AS Amount (Rs) 250000
AS Number U000000854929182 dated 25/03/2021
TS Amount (Rs) 250000
TS Number TS/800/2023_26_1_1 dated 17/03/2023
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 1000
Capacity in MLD 0.00
Actual Project Completion Date 02 Nov 2023
Coverage Replacing damaged GI pipes at Oojappara due to road widening in Keerampara Panchayath

Packages

No. Project Name Location View
1 DEPOSIT-ARWSS to Keerampara-Replacing damaged GI pipes-ARWSS to Keerampara-Replacing damaged GI pipes at Oojappara due to road widening in Keerampara Panchayath-Pipeline Work Kothamangalam Sn 2

Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 Nov 2023 Work completed Kothamangalam PH Sn 2 - AE
30 Oct 2023 Work in progress Kothamangalam PH Sn 2 - AE
27 Oct 2023 Agreement executed Kothamangalam PH Sn 2 - AE
24 Oct 2023 Agreement executed Kothamangalam PH Sn 2 - AE
21 Oct 2023 Agreement executed Kothamangalam PH Sn 2 - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 13/09/2023
Scheduled date of Completion of the Project 12 Oct 2023
Expected date of Completion 12/10/2023

Processing Dates

AS Date 17 Mar 2021
TS Date 17 Mar 2023

Other details