DEPOSIT-Janakeeyasoothranam - IWSS to Irinjalakuda- Replacing the existing 150mm & 250mm Distribution lines at Puttingal road inconnection with the culvert widening in Irinjalakuda Municipality

Project DEPOSIT-Janakeeyasoothranam - IWSS to Irinjalakuda- Replacing the existing 150mm & 250mm Distribution lines at Puttingal road inconnection with the culvert widening in Irinjalakuda Municipality
Project Code TCRDEPO112213329
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Replacing the existing 150mm & 250mm Distribution lines at Puttingal road inconnection with the culvert widening in Irinjalakuda Municipality
Status On-going
District Thrissur
Executing Office Irinjalakkuda PH Sn
AS Amount (Rs) 1000000
AS Number PW2-4705/21
TS Amount (Rs) 1700000
TS Number WRD/KWA-CE(CR)/EST_TS/19135/2023_5_1_1
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 IWSS to Irinjalakuda- Replacing the existing 150mm & 250mm Distribution lines at Puttingal road inconnection with the culvert widening in Irinjalakuda Municipality Irinjalakkuda PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Feb 2024 TECHNICAL SANCTION issued on 01.02.2024 Irinjalakkuda PH Dn EE
01 Jan 2024 Recasted Eastimate is Submitted Irinjalakuda AE
29 Jul 2023 Estimate to be re-casted after the joint inspection with Muncipal Engineer and Councillor. Irinjalakuda AE
22 Jun 2023 Estimate to be re-casted after the joint inspection with Muncipal Engineer and Councillor. Irinjalakuda AE
10 Apr 2023 Estimate to be re-casted after the joint inspection with Muncipal Engineer and Councillor. Irinjalakuda AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 11/11/2022
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion 30/06/2023

Processing Dates

AS Date 05 Dec 2023
TS Date 01 Jan 2024

Other details