Amrut 2.0- Vaikom Municipality-Existing Water Line Replacement and New Water Connection-Implementation-Pipe line Work

Project Amrut 2.0- Vaikom Municipality-Existing Water Line Replacement and New Water Connection-Implementation-Pipe line Work
Project Code KTMAMRUT 2022314110
Type Main project
Funding Agency AMRUT 2
Category AMRUT 2
Type of scheme Water Supply
Scheme
Description Existing Water Line Replacement and New Water Connection-Implementation
Status On-going
District Kottayam
Executing Office Kaduthuruthy PH Dn
AS Amount (Rs) 71600000
AS Number GO(Rt) 473/2023/LSGD
TS Amount (Rs) 60300000
TS Number WRD/KWA-CE(SR)/EST_TS/8481/2022_26_1_1
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted 3000
Capacity in MLD 45.00
Actual Project Completion Date Date is not specified
Coverage Vaikom Municipality
Implementation Schedule Download

Packages

No. Project Name Location View
1 Amrut 2.0 Vaikom Municipality-Existing Water Line Replacement And New Water Connection-Implementation-Pipe Line Work Vaikom Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
15 May 2024 fhtc work in ward 19,3nos given , ,Total 90 mm PVC =6325.47mtr, 110 mm PVC=2833.45 mtr, total 63 mm PVC=2915.7mtr, TOTAL FHTC-657 Vaikom - AE
14 May 2024 fhtc work in ward 19,3nos given , ,Total 90 mm PVC =6325.47mtr, 110 mm PVC=2833.45 mtr, total 63 mm PVC=2915.7mtr, TOTAL FHTC-654 Vaikom - AE
13 May 2024 fhtc work in ward 12,Inter connection work at ward 20,3nos given , ,Total 90 mm PVC =6325.47mtr, 110 mm PVC=2833.45 mtr, total 63 mm PVC=2915.7mtr, TOTAL FHTC-651 Vaikom - AE
12 May 2024 fhtc work in ward 19,Inter connection work at ward 23,4 nos given , ,Total 90 mm PVC =6325.47mtr, 110 mm PVC=2833.45 mtr, total 63 mm PVC=2915.7mtr, TOTAL FHTC-648 Vaikom - AE
11 May 2024 fhtc work in ward 19,Inter connection work at ward 23,2nos given , 5 nos given,Total 90 mm PVC =6325.47mtr, 110 mm PVC=2833.45 mtr, total 63 mm PVC=2915.7mtr, TOTAL FHTC-644 Vaikom - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project 03 Jul 2024
Expected date of Completion 03/07/2024

Processing Dates

AS Date 23 Feb 2023
TS Date 18 Apr 2023

Other details

Project Officers View