Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

KIIFB-WSS to Thrissur Corporation and adjoining 17 panchayaths-Package 1

Project KIIFB-WSS to Thrissur Corporation and adjoining 17 panchayaths-Package 1
Project Code TCRKIIFB0117503P1
Type Package
Main Project KIIFB-WSS to Thrissur Corporation and adjoining panchayaths
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Description Components a) 12 m dia well cum pump house at Thirukuzhi b) RW Pump set-530HP (6nos 2nos standby) c) RWPM - 1320mm MS Pipe(15mm thick)- 3350m d) 1000kVA Transformer-2nos and structure e) Retaining wall at Intake Well site f) Water Treatment Plant 100 MLD (Super Pulsator technology) and providing SCADA arrangements g) Surge arrester in 1320mm Raw water pumping main h) Site levelling and retaining wall at WTP site i) Transformer at WTP Site
Status On-going
District Thrissur
Executing Office Nattika Project Dn
TS Amount (Rs)
TS Number
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion Date is not specified

Other details

Project Schedule View
Project Components View
Project Officers View

Location

Project Status Updations See All Status Updations

Nattika Project Dn AE4
Date: 02/06/2021

Work has started | 0% Completed

As per letter received from ACS to government and chief engineer central region kwa on 28/05/2021 it was that AS for 268 cr could not be accorded. And instructed to limit the funding to 185 cr. The estimate work for 185 cr completed.DER will be being prepared and will submit by next week.Nattika Project Dn .

Nattika Project Dn AE4
Date: 01/06/2021

Work has started | 0% Completed

DER submitted to WRD on 21/01/2021 for obtain revised AS. Awaiting for revised AS.