DRW 2025 - Water Supply Schems RWSS to Vythiri - Cleaning of well and infiltration gallery at Hospaitalkunnu in Vythiri GP

Project DRW 2025 - Water Supply Schems RWSS to Vythiri - Cleaning of well and infiltration gallery at Hospaitalkunnu in Vythiri GP
Project Code WYDGOK022517676P1
Type Package
Main Project DRW 2025 - Water Supply Schems RWSS to Vythiri - Cleaning of well and infiltration gallery at Hospaitalkunnu in Vythiri GP
Funding Agency GOK
Category DRW
Type of scheme Water Supply
Scheme 4215-01-800-89
Description DRW 2025 - Water Supply Schems RWSS to Vythiri - Cleaning of well and infiltration gallery at Hospaitalkunnu in Vythiri GP
Status On-going
District Wayanad
Executing Office Kalpetta PH Sn 2
Agreement Number
Agreement Date
TS Amount (Rs) 285000
TS Number WRD/KWA-CE(NR)/EST_TS/4416/2025
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 10/04/2025
Scheduled date of Completion as per agreement 09 Jul 2025
Expected date of Completion 09/07/2025

Processing Dates

TS Date 04 Apr 2025
Estimate Approval 04 Apr 2025
NIT Approval 06 Mar 2025
Tender Closing 14 Mar 2025
Technichal Pre-Qualification 15 Mar 2025
Price bid opening 15 Mar 2025

Approval Dates

Workorder Date 09 Apr 2025
NA 10 Apr 2025

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kalpetta PH Sn 2 - AE
Date: 02/08/2025

Work has been completed | 100% Completed

e-Bill under division..

Kalpetta PH Sn 2 - AE
Date: 04/06/2025

Work has been completed | 100% Completed

e-Bill under division..