Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

AMRUT - SAAP 2015-16 - Water supply works in Kollam Corporation

Project AMRUT - SAAP 2015-16 - Water supply works in Kollam Corporation
Project Code KLMAMRUT03165726
Type Main project
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description Various works in Kollam corporation
Status Completed
District Kollam
Executing Office Kollam PH Dn
AS Amount (Rs) 65900000
AS Number Go(Rt) No. 1329/2016/LSGD dated 20/03/2016
TS Amount (Rs) 65900000
TS Number Reg .No. 7681/2019-2020
Total Bill Submitted (Rs) 57080000
Total Bill Paid (Rs) 57080000
Population Benefitted 7200
Capacity in MLD 5.00
Actual Project Completion Date Date is not specified
Coverage Various works in Kollam corporation

Packages

No. Project Name Location View
1 AMRUT- Improvement of existing WS System-Extension of 250mm DI K9 pipe line from Madan nada Junction to Polayathodu junction in Kollam Corporation Kollam PH Dn
2 Amrut- Improvement of Kollam Water Supply Scheme in Division No-7 to 11 in Kollam Corporation - Replacement of damaged pump set Kollam PH Dn
3 AMRUT- Improvement of water supply in Kollam corporation-Supply and installation of Chlorinator system to tube well pump houses to Kollam Corporation Kollam PH Dn
4 AMRUT- Replacement of 50 HP/75 HP vertical turbine pump set in Booster pump house at Anandavalleeswaram Kollam PH Dn
5 AMRUT- Replacement of contaminated AC pipe lines AC pipe lines in Kollam Corporation- Laying distribution main from Pazhayattinkuzhy OHSR to Ammannada Division in Kollam Corporation Kollam PH Dn
6 AMRUT-Replacement of contaminated pipe lines in Kollam Corporation -Laying distribution mains to Andamukkam -Thamarakkulam - Contonment area from OH tank, near Parvathy mill, Chinnakkada to Mundakkal Beach area from No.III/IV tank Kollam PH Dn
7 AMRUT- Supply , Erection and commissioning of Chlorinator system to Booster pump house at Anandavalleeswaram with 100 kg Chlorine cylinder Kollam PH Dn
8 Improvement of Kollam WSS Division No. 7 to 11 in Kollam Corporation (Laying 110mm PVC 2500m, 90mm PVC 4500m). Kollam PH Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
15 Dec 2020 completed Kollam PH Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 01/09/2016
Scheduled date of Completion of the Project 08 Jul 2020
Expected date of Completion 08/07/2020

Processing Dates

AS Date 26 Mar 2016
TS Date 19 Apr 2016

Other details

Project Officers View