| Project | Jal Jeevan Mission- Kasaragod District- Kuttikol Grama Panchayath- ARWSS to Munnad Bedadka and Kuttikol Villages Phase II - Laying distribution System and providing FHTC-Construction of 2 lakhs litres OH Tank at Meeyanganam-Balance work |
|---|---|
| Project Code | KGDJJM08202906P3 |
| Type | Package |
| Main Project | Jal Jeevan Mission- Kasaragod District- Kuttikol Grama Panchayath- ARWSS to Munnad Bedadka and Kuttikol Villages Phase II - Laying distribution System and providing FHTC |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Jal Jeevan Mission- Kasaragod District- Kuttikol Grama Panchayath- ARWSS to Munnad Bedadka and Kuttikol Villages Phase II - Laying distribution System and providing FHTC-Construction of 2 lakhs litres OH Tank at Meeyanganam-Balance work |
| Status | On-going |
| District | Kasaragod |
| Executing Office | Bovikkanam WSP Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 37000000 |
| TS Number | 8761/2023-26-1-1 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | Date is not specified |
|---|---|
| Scheduled date of Completion as per agreement | 04 Apr 2024 |
| Expected date of Completion | 31/12/2024 |
| TS Date | 09 Aug 2023 |
|---|---|
| Estimate Approval | 09 Aug 2023 |
| Tender Closing | 16 Aug 2023 |
| Price bid opening | 21 Aug 2023 |
| Workorder Date | 05 Sep 2023 |
|---|---|
| NA | 25 Sep 2023 |
| Bovikkanam WSP Sn AE |
| Date: 26/05/2026 |
Work in progress | 1% Completed
Site handed over on 05/10/2023.
| Bovikkanam WSP Sn AE |
| Date: 11/05/2026 |
Work in progress | 1% Completed
Site handed over on 05/10/2023.