Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

DAWSS to Edappal & adj.pts -supply and fixing new CI sluice valves in place of old valves which are not functioning properly ie 350mm ,300mm,250mm and 200mm in Gravity and distribution lines .

Project DAWSS to Edappal & adj.pts -supply and fixing new CI sluice valves in place of old valves which are not functioning properly ie 350mm ,300mm,250mm and 200mm in Gravity and distribution lines .
Project Code MLPGOK06217979
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description DAWSS to Edappal & adj.pts -supply and fixing new CI sluice valves in place of old valves which are not functioning properly ie 350mm ,300mm,250mm and 200mm in Gravity and distribution lines .
Status Dropped
District Malappuram
Executing Office Edappal PH Dn
AS Amount (Rs) 400000
AS Number KWA/JB/PIU-1/AE-4/Annual plan /2021-22 (1)
TS Amount (Rs)
TS Number
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted 500
Capacity in MLD 0.10
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 DAWSS to Edappal & adj.pts -supply and fixing new CI sluice valves in place of old valves which are not functioning properly ie 350mm ,300mm,250mm and 200mm in Gravity and distribution lines . Edappal Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
23 Aug 2022 As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan Edappal Sn AE
12 Aug 2022 As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan Edappal Sn AE
05 Aug 2022 As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan Edappal Sn AE
01 Aug 2022 As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan Edappal Sn AE
21 Jul 2022 As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan Edappal Sn AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project 31 Mar 2022
Expected date of Completion 31/03/2022

Processing Dates

AS Date 02 Jun 2021

Other details

Project Officers View