DAWSS to Edappal & adj.pts -supply and fixing new CI sluice valves in place of old valves which are not functioning properly ie 350mm ,300mm,250mm and 200mm in Gravity and distribution lines .
DAWSS to Edappal & adj.pts -supply and fixing new CI sluice valves in place of old valves which are not functioning properly ie 350mm ,300mm,250mm and 200mm in Gravity and distribution lines .
Project Code
MLPGOK06217979
Type
Main project
Funding Agency
GOK
Category
State plan
Type of scheme
Water Supply
Scheme
2215-02-106-97
Description
DAWSS to Edappal & adj.pts -supply and fixing new CI sluice valves in place of old valves which are not functioning properly ie 350mm ,300mm,250mm and 200mm in Gravity and distribution lines .
Status
Dropped
District
Malappuram
Executing Office
Edappal PH Dn
AS Amount (Rs)
400000
AS Number
KWA/JB/PIU-1/AE-4/Annual plan /2021-22 (1)
TS Amount (Rs)
TS Number
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
500
Capacity in MLD
0.10
Actual Project Completion Date
Date is not specified
Coverage
Packages
No.
Project Name
Location
View
1
DAWSS to Edappal & adj.pts -supply and fixing new CI sluice valves in place of old valves which are not functioning properly ie 350mm ,300mm,250mm and 200mm in Gravity and distribution lines .
Edappal Sn
Overall Project Status
Status Date
Overall Project Status
Project Officer
Contact
23 Aug 2022
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE
12 Aug 2022
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE
05 Aug 2022
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE
01 Aug 2022
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE
21 Jul 2022
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan