| Project | Jal jeevan Mission-2021-22-Upgradation and shifting of quality control sub district lab Sulthan bathery for NABL accrediation fo chemical lab-Civil and electrical works |
|---|---|
| Project Code | WYDJJM09208515P1 |
| Type | Package |
| Main Project | Jal jeevan Mission-2021-22-Upgradation and shifting of quality control sub district lab Sulthan bathery for NABL accrediation fo chemical lab-Civil and electrical works |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Jal jeevan Mission-2021-22-Upgradation and shifting of quality control sub district lab Sulthan bathery for NABL accrediation fo chemical lab-Civil and electrical works |
| Status | On-going |
| District | Wayanad |
| Executing Office | Wayanad QC Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 3739000 |
| TS Number | TS/2021-2022/2021/21206 for Civil work TS/2021-2022/2021/22424 for Electrical work |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 16/10/2021 |
|---|---|
| Scheduled date of Completion as per agreement | 07 Mar 2022 |
| Expected date of Completion | 01/03/2022 |
| TS Date | 16 Oct 2021 |
|---|---|
| Estimate Approval | 16 Oct 2021 |
| Tender Closing | 06 Nov 2021 |
| Price bid opening | 10 Nov 2021 |
| Workorder Date | 08 Dec 2021 |
|---|---|
| NA | 16 Dec 2021 |
| Kozhikode QC Sub Dn AEE |
| Date: 07/03/2022 |
Work has been completed | 100% Completed
Civil and electrical work of the lab is completed.
| Kozhikode QC Sub Dn AEE |
| Date: 01/03/2022 |
Work in progress | 95% Completed
Painting and Aluminium partition works.