- Home
- AMRUT-2016-17- Construction of new treat...
AMRUT-2016-17- Construction of new treatment plant of 20MLD at Peechi (AS -17.3Cr)
Project |
AMRUT-2016-17- Construction of new treatment plant of 20MLD at Peechi (AS -17.3Cr) |
Project Code |
TCRGOI0917538 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
Project Components 1) Supply and erection and commissioning of clear water centrifugal motor & pumpsets having Discharge – 251.21 LPS and Head - 27 m one as stand bye and related works.
2) Supply, installation of 225mm Electromagnetic flowmeter and related works. 3)For interconnection of pump sets delivery end with proposed 500 mm DI K9 raw water pumping main outside the pump house. 4) Design, construction and commissioning of Water treatment plant of 20 MLD output capacity conventional type, complete in all respects, including construction of the structures for the various units, supply and installation of Mechanical and Electrical equipment, obataining power connection including the charges remitted to KSEB and all other connected works, including trial run and commissioning of the plant. 5) Formation of external approach road and internal roads formation width 8.0m and concrete surface 4.0 m wide - 600 m |
Status |
Completed |
District |
Thrissur |
Executing Office |
Nattika Project Dn |
AS Amount (Rs) |
173000000
|
AS Number |
G.O(Rt) no.3170/2017/LSGD dt 28.09.2017 |
TS Amount (Rs) |
108603639 |
TS Number |
TS/2018-2019/2018/802 Dt. 31.05.2018 |
Total Bill Submitted (Rs) |
100803367 |
Total Bill Paid (Rs) |
100803367 |
Population Benefitted |
133000 |
Capacity in MLD |
20.00 |
Actual Project Completion Date |
31 Jan 2022 |
Coverage |
(1) Ultimate Benefited Population in 2020 is 133000
(2) Quantity of water to be produced - 20MLD
(3) Expected annual revenue when project is completed - Rs. 7,86,60,000/-
(4) Time overrun in Days/ weeks - 40 weeks (as on 17/11/2020)
|
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT-2016-17- Construction of new treatment plant of 20MLD WTP at Peechi - additional work for the construction of 1.80 LL Wash water recycling sump and connected works at Peechi |
Nattika Project Dn |
|
2 |
AMRUT-Construction of new treatment plant of 20MLD at Peechi. |
Nattika Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
04 Jul 2022 |
WTP fully functional from 25/03/2021 |
Nattika Project Dn AE 4 |
|
09 Jun 2022 |
WTP fully functional from 25/03/2021 |
Nattika Project Dn AE 4 |
|
02 Jun 2022 |
WTP fully functional from 25/03/2021 |
Nattika Project Dn AE 4 |
|
01 Jun 2022 |
WTP fully functional from 25/03/2021 |
Nattika Project Dn AE 4 |
|
01 Jun 2022 |
WTP fully functional from 25/03/2021 |
Nattika Project Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
19/03/2019 |
Scheduled date of Completion of the Project |
16 Jan 2020 |
Expected date of Completion |
28/02/2022 |
Processing Dates
AS Date |
28 Sep 2017 |
TS Date |
31 May 2018 |