Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

CWSS to Anadu,Kurupuzha and Palode Villages-Phase-II

Project CWSS to Anadu,Kurupuzha and Palode Villages-Phase-II
Project Code TVMGOK0818664
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description Package I: 1. Supplying,Laying,Testing and Commissioning of 300mm DI K-9 CWPM from WTP at Nanniyode to proposed 10LL GLSR at Nanniyode(Anakkuzhy),2.150mm DI K-9 CWPM to Existing GLSR at Nanniyode, 3. 10LL Capacity GLSR at Nanniyode(Anakkuzhy) ,4. Construction od Indoor Transformer room at WTP,Nanniyode 5. Construction of Indoor Transformer room near Well cum Pump House at Palode. Package II Distribution Network of Zone-II and Renovation of existing GLSR at Nanniyode Package III 1. Supply,Erection,Testing & Commissioning of Vertical Turbine Pump Set at Raw Water Pump House,Palode 2. Supply,Erection,Testing & Commissioning of Cenrifugal Pump Set at WTP,Nanniyode 3. Supply,Erection,Testing & Commissioning of 630 KVA Indoor Transformer at WTP site,Nanniyode 4. Supply,Erection,Testing & Commissioning of 250 KVA Indoor Transformer Well Cum Pump House site,Palode
Status On-going
District Thiruvananthapuram
Executing Office Trivandrum Project Dn
AS Amount (Rs) 160000000
AS Number G.O.(Rt)No.571/2018/WRD
TS Amount (Rs) 147160000
TS Number TS/2020-2021/2019/8864; TS/2020-2021/2019/8866; TS/2020-2021/2019/8867
Total Bill Submitted (Rs) 55683292
Total Bill Paid (Rs) 55683292
Population Benefitted 35347
Capacity in MLD 2.91
Actual Project Completion Date 03 Jun 2022
Coverage Design Population for the entire scheme in 2030 is 114704 , Design Population for phase II (2030) is 35347
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 CWSS to Anadu,Kurupuzha and Palode Villages-Phase-II :- Package 1 &2 Trivandrum Project Dn
2 CWSS to Anadu,Kurupuzha and Palode Villages-Phase-II :- Package 3 Trivandrum Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 Feb 2024 Package I: 1. Supplying,Laying,Testing and Commissioning of 300mm DI K-9 CWPM from WTP at Nanniyode to proposed 10LL GLSR at Nanniyode(Anakkuzhy),2.150mm DI K-9 CWPM to Existing GLSR at Nanniyode, 3. 10LL Capacity GLSR at Nanniyode(Anakkuzhy) ,4. Construction od Indoor Transformer room at WTP,Nanniyode 5. Construction of Indoor Transformer room near Well cum Pump House at Palode. Package II Distribution Network of Zone-II and Renovation of existing GLSR at Nanniyode Package III 1. Supply,Erection,Testing & Commissioning of Vertical Turbine Pump Set at Raw Water Pump House,Palode -95% 2. Supply,Erection,Testing & Commissioning of Cenrifugal Pump Set at WTP,Nanniyode 3. Supply,Erection,Testing & Commissioning of 630 KVA Indoor Transformer at WTP site,Nanniyode 4. Supply,Erection,Testing & Commissioning of 250 KVA Indoor Transformer Well Cum Pump House site,Palode-75% Thiruvananthapuram Project - AE 11
30 Apr 2022 ackage 1&2 :Structure completed at GLSR Anakkuzhy, Structure completed at transformer room near WTP Nanniyode, Roof concrete completed at transformer room near Well , Inside concrete completed at existing GLSR Nanniyode Total pipe laid, 90mm pvc 6kg = 14212m, 90mm pvc 8kg = 1850m, 90 mm PVC 10 kg =11271m, 110mm pvc 6kg= 240m,160mm pvc 10 kg= 1050m, 160mm PVC 6kg =894m, 140mm pvc 6kg = 336m, 14mm pvc 10kg = 840m Package 3 : Raw water and Clear water pumpsets arrived.work can be resumed after completion of Trasformer rooms at Nanniyode and palode Thiruvananthapuram Proj Dn AEE 4
14 Mar 2022 ackage 1&2 :Structure completed at GLSR Anakkuzhy, Structure completed at transformer room near WTP Nanniyode, Roof concrete completed at transformer room near Well , Inside concrete completed at existing GLSR Nanniyode Total pipe laid, 90mm pvc 6kg = 14212m, 90mm pvc 8kg = 1850m, 90 mm PVC 10 kg =11271m, 110mm pvc 6kg= 240m,160mm pvc 10 kg= 1050m, 160mm PVC 6kg =894m, 140mm pvc 6kg = 336m, 14mm pvc 10kg = 840m Package 3 : Raw water and Clear water pumpsets arrived Thiruvananthapuram Proj Dn AEE 4
14 Mar 2022 Package 1&2 :Structure completed at GLSR Anakkuzhy, Structure completed at transformer room near WTP Nanniyode, Pile cap completed at transformer room near Well , Inside concrete completed at existing GLSR Nanniyode Total pipe laid, 90mm pvc 6kg = 14212m, 90mm pvc 8kg = 1850m, 90 mm PVC 10 kg =11271m, 110mm pvc 6kg= 240m,160mm pvc 10 kg= 1050m, 160mm PVC 6kg =894m, 140mm pvc 6kg = 336m, 14mm pvc 10kg = 840m Package 3 : Raw water and Clear water pumpsets arrived Thiruvananthapuram Proj Dn AEE 4
10 Jan 2022 Package 1&2 :Structure completed at GLSR Anakkuzhy, Structure completed at transformer room near WTP Nanniyode, Pile cap completed at transformer room near Well , Inside concrete completed at existing GLSR Nanniyode Total pipe laid, 90mm pvc 6kg = 14212m, 90mm pvc 8kg = 1850m, 90 mm PVC 10 kg =11271m, 110mm pvc 6kg= 240m,160mm pvc 10 kg= 1050m, 160mm PVC 6kg =894m, 140mm pvc 6kg = 336m, 14mm pvc 10kg = 840m Package 3 : Raw water and Clear water pumpsets arrived Thiruvananthapuram Project - AE 11

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 10/02/2021
Scheduled date of Completion of the Project 03 Jun 2022
Expected date of Completion 03/06/2022

Processing Dates

AS Date 01 Aug 2018
TS Date 21 Aug 2020

Other details

Project Officers View