Status Date |
Overall Project Status |
Project Officer |
Contact |
13 Feb 2024 |
Package I: 1. Supplying,Laying,Testing and Commissioning of 300mm DI K-9 CWPM from WTP at Nanniyode to proposed 10LL GLSR at Nanniyode(Anakkuzhy),2.150mm DI K-9 CWPM to Existing GLSR at Nanniyode, 3. 10LL Capacity GLSR at Nanniyode(Anakkuzhy) ,4. Construction od Indoor Transformer room at WTP,Nanniyode 5. Construction of Indoor Transformer room near Well cum Pump House at Palode. Package II Distribution Network of Zone-II and Renovation of existing GLSR at Nanniyode Package III 1. Supply,Erection,Testing & Commissioning of Vertical Turbine Pump Set at Raw Water Pump House,Palode -95% 2. Supply,Erection,Testing & Commissioning of Cenrifugal Pump Set at WTP,Nanniyode 3. Supply,Erection,Testing & Commissioning of 630 KVA Indoor Transformer at WTP site,Nanniyode 4. Supply,Erection,Testing & Commissioning of 250 KVA Indoor Transformer Well Cum Pump House site,Palode-75% |
Thiruvananthapuram Project - AE 11 |
|
30 Apr 2022 |
ackage 1&2 :Structure completed at GLSR Anakkuzhy, Structure completed at transformer room near WTP Nanniyode, Roof concrete completed at transformer room near Well , Inside concrete completed at existing GLSR Nanniyode Total pipe laid, 90mm pvc 6kg = 14212m, 90mm pvc 8kg = 1850m, 90 mm PVC 10 kg =11271m, 110mm pvc 6kg= 240m,160mm pvc 10 kg= 1050m, 160mm PVC 6kg =894m, 140mm pvc 6kg = 336m, 14mm pvc 10kg = 840m Package 3 : Raw water and Clear water pumpsets arrived.work can be resumed after completion of Trasformer rooms at Nanniyode and palode |
Thiruvananthapuram Proj Dn AEE 4 |
|
14 Mar 2022 |
ackage 1&2 :Structure completed at GLSR Anakkuzhy, Structure completed at transformer room near WTP Nanniyode, Roof concrete completed at transformer room near Well , Inside concrete completed at existing GLSR Nanniyode Total pipe laid, 90mm pvc 6kg = 14212m, 90mm pvc 8kg = 1850m, 90 mm PVC 10 kg =11271m, 110mm pvc 6kg= 240m,160mm pvc 10 kg= 1050m, 160mm PVC 6kg =894m, 140mm pvc 6kg = 336m, 14mm pvc 10kg = 840m Package 3 : Raw water and Clear water pumpsets arrived |
Thiruvananthapuram Proj Dn AEE 4 |
|
14 Mar 2022 |
Package 1&2 :Structure completed at GLSR Anakkuzhy, Structure completed at transformer room near WTP Nanniyode, Pile cap completed at transformer room near Well , Inside concrete completed at existing GLSR Nanniyode Total pipe laid, 90mm pvc 6kg = 14212m, 90mm pvc 8kg = 1850m, 90 mm PVC 10 kg =11271m, 110mm pvc 6kg= 240m,160mm pvc 10 kg= 1050m, 160mm PVC 6kg =894m, 140mm pvc 6kg = 336m, 14mm pvc 10kg = 840m Package 3 : Raw water and Clear water pumpsets arrived |
Thiruvananthapuram Proj Dn AEE 4 |
|
10 Jan 2022 |
Package 1&2 :Structure completed at GLSR Anakkuzhy, Structure completed at transformer room near WTP Nanniyode, Pile cap completed at transformer room near Well , Inside concrete completed at existing GLSR Nanniyode Total pipe laid, 90mm pvc 6kg = 14212m, 90mm pvc 8kg = 1850m, 90 mm PVC 10 kg =11271m, 110mm pvc 6kg= 240m,160mm pvc 10 kg= 1050m, 160mm PVC 6kg =894m, 140mm pvc 6kg = 336m, 14mm pvc 10kg = 840m
Package 3 : Raw water and Clear water pumpsets arrived |
Thiruvananthapuram Project - AE 11 |
|