Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

State Plan - 2020-21-TSS- E- Block Zone II -Laying 700mm dia RCC NP3 pipe sewer main from Jagathy towards common manhole Ch.512m to 785m & Interconnection of 700mm dia DI pipe between Jagathy Chadiyara sewer main and parallel main across Killi river and constructing 450mm dia board cast in situ piles inside of river and connected works.Ch.649m to 679m.

Project State Plan - 2020-21-TSS- E- Block Zone II -Laying 700mm dia RCC NP3 pipe sewer main from Jagathy towards common manhole Ch.512m to 785m & Interconnection of 700mm dia DI pipe between Jagathy Chadiyara sewer main and parallel main across Killi river and constructing 450mm dia board cast in situ piles inside of river and connected works.Ch.649m to 679m.
Project Code TVMGOK10206732
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description State Plan - 2020-21-TSS- E- Block Zone II -Laying 700mm dia RCC NP3 pipe sewer main from Jagathy towards common manhole Ch.512m to 785m & Interconnection of 700mm dia DI pipe between Jagathy Chadiyara sewer main and parallel main across Killi river and constructing 450mm dia board cast in situ piles inside of river and connected works.Ch.649m to 679m.
Status On-going
District Thiruvananthapuram
Executing Office Plamoodu project Sn
AS Amount (Rs) 18080000
AS Number KWA/JB/PIU1/AE1/12/2021
TS Amount (Rs) 18000000
TS Number TS / 417/2022
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 2000
Capacity in MLD 0.01
Actual Project Completion Date 29 Feb 2024
Coverage Zone II E Block
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 State Plan - 2020-21-TSS- E- Block Zone II -Laying 700mm dia RCC NP3 pipe sewer main from Jagathy towards common manhole Ch.512m to 785m & Interconnection of 700mm dia DI pipe between Jagathy Chadiyara sewer main and parallel main across Killi river and constructing 450mm dia board cast in situ piles inside of river and connected works.Ch.649m to 679m. Plamoodu project Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 May 2024 Tree cutting sanction received from the Forest Department and auction notice published several times and one auction conducted but no offer received. Hence as per the oral direction from the higher authority the trees were cut and stacked at site on 20/02/2024 at department expence as it was an obstruction for the progress of the work .160.15 m of 700 mm RCC pipe laid . Pipe supplied on 17/10/2023 , 21/10/2023 and 12/02/2024 . MH 1 to MH 9 completed . Interconnection from existing MH at bund road done on 04/03/2024 . Plamoodu Sewerage Project Sn AE
13 May 2024 Tree cutting sanction received from the Forest Department and auction notice published several times and one auction conducted but no offer received. Hence as per the oral direction from the higher authority the trees were cut and stacked at site on 20/02/2024 at department expence as it was an obstruction for the progress of the work .160.15 m of 700 mm RCC pipe laid . Pipe supplied on 17/10/2023 , 21/10/2023 and 12/02/2024 . MH 1 to MH 9 completed . Interconnection from existing MH at bund road done on 04/03/2024 . Plamoodu Sewerage Project Sn AE
10 May 2024 Tree cutting sanction received from the Forest Department and auction notice published several times and one auction conducted but no offer received. Hence as per the oral direction from the higher authority the trees were cut and stacked at site on 20/02/2024 at department expence as it was an obstruction for the progress of the work .160.15 m of 700 mm RCC pipe laid . Pipe supplied on 17/10/2023 , 21/10/2023 and 12/02/2024 . MH 1 to MH 9 completed . Interconnection from existing MH at bund road done on 04/03/2024 . Plamoodu Sewerage Project Sn AE
08 May 2024 Tree cutting sanction received from the Forest Department and auction notice published several times and one auction conducted but no offer received. Hence as per the oral direction from the higher authority the trees were cut and stacked at site on 20/02/2024 at department expence as it was an obstruction for the progress of the work .160.15 m of 700 mm RCC pipe laid . Pipe supplied on 17/10/2023 , 21/10/2023 and 12/02/2024 . MH 1 to MH 9 completed . Interconnection from existing MH at bund road done on 04/03/2024 . Plamoodu Sewerage Project Sn AE
06 May 2024 Tree cutting sanction received from the Forest Department and auction notice published several times and one auction conducted but no offer received. Hence as per the oral direction from the higher authority the trees were cut and stacked at site on 20/02/2024 at department expence as it was an obstruction for the progress of the work .160.15 m of 700 mm RCC pipe laid . Pipe supplied on 17/10/2023 , 21/10/2023 and 12/02/2024 . MH 1 to MH 9 completed . Interconnection from existing MH at bund road done on 04/03/2024 . Plamoodu Sewerage Project Sn AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 13/05/2022
Scheduled date of Completion of the Project 31 Mar 2024
Expected date of Completion 31/03/2024

Processing Dates

AS Date 13 May 2022
TS Date 19 Jan 2023

Other details

Project Officers View