State Plan - 2020-21-TSS- E- Block Zone II -Laying 700mm dia RCC NP3 pipe sewer main from Jagathy towards common manhole Ch.512m to 785m & Interconnection of 700mm dia DI pipe between Jagathy Chadiyara sewer main and parallel main across Killi river and constructing 450mm dia board cast in situ piles inside of river and connected works.Ch.649m to 679m.
Project |
State Plan - 2020-21-TSS- E- Block Zone II -Laying 700mm dia RCC NP3 pipe sewer main from Jagathy towards common manhole Ch.512m to 785m & Interconnection of 700mm dia DI pipe between Jagathy Chadiyara sewer main and parallel main across Killi river and constructing 450mm dia board cast in situ piles inside of river and connected works.Ch.649m to 679m. |
Project Code |
TVMGOK10206732 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
State Plan - 2020-21-TSS- E- Block Zone II -Laying 700mm dia RCC NP3 pipe sewer main from Jagathy towards common manhole Ch.512m to 785m & Interconnection of 700mm dia DI pipe between Jagathy Chadiyara sewer main and parallel main across Killi river and constructing 450mm dia board cast in situ piles inside of river and connected works.Ch.649m to 679m. |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Plamoodu project Sn |
AS Amount (Rs) |
18080000
|
AS Number |
KWA/JB/PIU1/AE1/12/2021 |
TS Amount (Rs) |
18000000 |
TS Number |
TS / 417/2022 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
2000 |
Capacity in MLD |
0.01 |
Actual Project Completion Date |
29 Feb 2024 |
Coverage |
Zone II E Block |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
State Plan - 2020-21-TSS- E- Block Zone II -Laying 700mm dia RCC NP3 pipe sewer main from Jagathy towards common manhole Ch.512m to 785m & Interconnection of 700mm dia DI pipe between Jagathy Chadiyara sewer main and parallel main across Killi river and constructing 450mm dia board cast in situ piles inside of river and connected works.Ch.649m to 679m. |
Plamoodu project Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
14 May 2024 |
Tree cutting sanction received from the Forest Department and auction notice published several times and one auction conducted but no offer received. Hence as per the oral direction from the higher authority the trees were cut and stacked at site on 20/02/2024 at department expence as it was an obstruction for the progress of the work .160.15 m of 700 mm RCC pipe laid . Pipe supplied on 17/10/2023 , 21/10/2023 and 12/02/2024 . MH 1 to MH 9 completed . Interconnection from existing MH at bund road done on 04/03/2024 . |
Plamoodu Sewerage Project Sn AE |
|
13 May 2024 |
Tree cutting sanction received from the Forest Department and auction notice published several times and one auction conducted but no offer received. Hence as per the oral direction from the higher authority the trees were cut and stacked at site on 20/02/2024 at department expence as it was an obstruction for the progress of the work .160.15 m of 700 mm RCC pipe laid . Pipe supplied on 17/10/2023 , 21/10/2023 and 12/02/2024 . MH 1 to MH 9 completed . Interconnection from existing MH at bund road done on 04/03/2024 . |
Plamoodu Sewerage Project Sn AE |
|
10 May 2024 |
Tree cutting sanction received from the Forest Department and auction notice published several times and one auction conducted but no offer received. Hence as per the oral direction from the higher authority the trees were cut and stacked at site on 20/02/2024 at department expence as it was an obstruction for the progress of the work .160.15 m of 700 mm RCC pipe laid . Pipe supplied on 17/10/2023 , 21/10/2023 and 12/02/2024 . MH 1 to MH 9 completed . Interconnection from existing MH at bund road done on 04/03/2024 . |
Plamoodu Sewerage Project Sn AE |
|
08 May 2024 |
Tree cutting sanction received from the Forest Department and auction notice published several times and one auction conducted but no offer received. Hence as per the oral direction from the higher authority the trees were cut and stacked at site on 20/02/2024 at department expence as it was an obstruction for the progress of the work .160.15 m of 700 mm RCC pipe laid . Pipe supplied on 17/10/2023 , 21/10/2023 and 12/02/2024 . MH 1 to MH 9 completed . Interconnection from existing MH at bund road done on 04/03/2024 . |
Plamoodu Sewerage Project Sn AE |
|
06 May 2024 |
Tree cutting sanction received from the Forest Department and auction notice published several times and one auction conducted but no offer received. Hence as per the oral direction from the higher authority the trees were cut and stacked at site on 20/02/2024 at department expence as it was an obstruction for the progress of the work .160.15 m of 700 mm RCC pipe laid . Pipe supplied on 17/10/2023 , 21/10/2023 and 12/02/2024 . MH 1 to MH 9 completed . Interconnection from existing MH at bund road done on 04/03/2024 . |
Plamoodu Sewerage Project Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
13/05/2022 |
Scheduled date of Completion of the Project |
31 Mar 2024 |
Expected date of Completion |
31/03/2024 |
Processing Dates
AS Date |
13 May 2022 |
TS Date |
19 Jan 2023 |