AMRUT 2.0 - KMWSS to Kodungallur Municipality-Providing 4000 FHTC to urban Householders including pipe laying work
Project Code
TCRAMRUT032313910
Type
Main project
Funding Agency
AMRUT
Category
AMRUT 2
Type of scheme
Water Supply
Scheme
AMRUT
Description
AMRUT 2.0 - KMWSS to Kodungallur Municipality-Providing 4000 FHTC to urban Householders including pipe laying work
Status
On-going
District
Thrissur
Executing Office
Kodungalloor PH Sn
AS Amount (Rs)
158000000
AS Number
GO(Rt)No. 677/2023/LSGD
TS Amount (Rs)
155100000
TS Number
WRD/KWA-CE(CR)/EST_TS/4559/2022_26_1_1
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
10810146
Population Benefitted
Capacity in MLD
Actual Project Completion Date
Date is not specified
Coverage
Packages
No.
Project Name
Location
View
1
AMRUT 2.0 - KMWSS to Kodungallur Municipality-Providing 4000 FHTC to urban Householders including pipe laying work
Kodungalloor PH Sn
Overall Project Status
Status Date
Overall Project Status
Project Officer
Contact
23 Apr 2024
Work is in progress and pipe laying 40 % (22Km) and providing FHTC95% (3800 Nos) completed. Financial progress 20% achieved,awaiting for road cutting permission from PWD/Municipality and contractor applied for time extension
Kodungallur AE
18 Mar 2024
Work is in progress and pipe laying 20 % (11Km) and providing FHTC88% (3500 Nos) completed. Financial progress 7.32% achieved,awaiting for road cutting permission from PWD/Municipality and contractor applied for time extension
Kodungallur AE
24 Feb 2024
Work is in progress and pipe laying 14 % (7 Km) and providing FHTC80% (3200 Nos) completed. Financial progress 7.32% achieved,awaiting for road cutting permission from PWD/Municipality and contractor applied for time extension
Kodungallur AE
24 Feb 2024
Work is in progress and pipe laying 14 % (7 Km) and providing FHTC80% (3200 Nos) completed. Financial progress 7.32% achieved,awaiting for road cutting permission from PWD/Municipality
Kodungallur AE
14 Feb 2024
Work is in progress and pipe laying 9 % (4.5 Km) and providing FHTC63% (2500 Nos) completed. Financial progress 7.32% achieved,awaiting for road cutting permission from PWD/Municipality