KIIFB - WSS to Thrissur Corporation and adjoining 17 panchayaths - Package 2&3

Project KIIFB - WSS to Thrissur Corporation and adjoining 17 panchayaths - Package 2&3
Project Code TCRKIIFB0117503P4
Type Package
Main Project KIIFB-WSS to Thrissur Corporation and adjoining panchayaths
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Supplying, laying, testing and commissioning of CWGM of 1200mm MS pipe from WTP to Kanimangalam,900 mm pipe from Kanimangalam to Nedupuzha and DI pipes of 800 mm dia from Kanimangalam to various tanks
Status On-going
District Thrissur
Executing Office Nattika Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 0
TS Number nill
Technical specification a) Clear water transmission mains - 800 mm DI k9 pipe b) Steel bridge for laying

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 15/04/2023
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion Date is not specified

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Nattika Project Dn AE 6
Date: 21/05/2026

Work in progress | 35% Completed

TS obtained on 23/02/2024, & TS file uploaded in PFMS on 04.04.2024 TS obtained from KIIFB on 20/04/2024. • 1 bid received, contractor quoted 5.22% above TPAC. • Tender submitted to CE for approval on 07/08/2025.TS obtained on 23/02/2024, & TS file uploaded in PFMS on 04.04.2024 TS obtained from KIIFB on 20/04/2024. • 1 bid received, contractor quoted 5.22% above TPAC. • Tender submitted to CE for approval on 07/08/2025.LOA issued on 28/10/2025.Agreement executed on 31/10/2025.900mm DI - 2660m, 800mm DI - 3225m, 1200mm MS pipe - 3987.98m are supplied. Balance Supply in progress .

Nattika Project Dn AE 6
Date: 14/05/2026

Work in progress | 35% Completed

TS obtained on 23/02/2024, & TS file uploaded in PFMS on 04.04.2024 TS obtained from KIIFB on 20/04/2024. • 1 bid received, contractor quoted 5.22% above TPAC. • Tender submitted to CE for approval on 07/08/2025.TS obtained on 23/02/2024, & TS file uploaded in PFMS on 04.04.2024 TS obtained from KIIFB on 20/04/2024. • 1 bid received, contractor quoted 5.22% above TPAC. • Tender submitted to CE for approval on 07/08/2025.LOA issued on 28/10/2025.Agreement executed on 31/10/2025.900mm DI - 2660m, 800mm DI - 3225m, 1200mm MS pipe - 3987.98m are supplied. Balance Supply in progress .