KIIFB-Augmentation of CWSS to Nattika Firka (Phase I)
Project |
KIIFB-Augmentation of CWSS to Nattika Firka (Phase I) |
Project Code |
TCRKIIFB1118506 |
Type |
Main project |
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
Package I-
a) Renovation of existing plant, well cum pumphouse
b) 9m dia well cum pumphouse
c) 265 HPVT Raw water pumpset- 2Nos
d) 700mm DI K9 RWPM- 2700m
e) 26MLD WTP- Lamela type plate settler
f) 11LL Clear water sump
g) 225HP C/F Clearwater pumpset-2 nos
h) compound wall, SCADA
i) 500KVA Transformer-2 Nos.
Package II-
a) 900mm DI K9 CWPM-7670M
b)800/700/500/300 DI K9 CWPM-7220M, fire hydrant,road restoration |
Status |
On-going |
District |
Thrissur |
Executing Office |
Nattika Project Dn |
AS Amount (Rs) |
699600000
|
AS Number |
WRD-025-04/APR/6/2013/KIIFB |
TS Amount (Rs) |
699600000 |
TS Number |
TS/2019-20/2019/13021 |
Total Bill Submitted (Rs) |
254000 |
Total Bill Paid (Rs) |
254000 |
Population Benefitted |
345000 |
Capacity in MLD |
26.00 |
Actual Project Completion Date |
24 Feb 2022 |
Coverage |
1. Covered Panchayaths - S.N. Puram, Mathilakam,
Perinjanam, Kaipamangalam, Edathiruthy, Valapad,
Nattika, Thalikulam, Vadanappilly and Engandiyur
2. Ultimate population in 2050 - 345000
3. Quantity of water to be produced- 26 MLD
|
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Augmentation of CWSS to Nattika Firka (Phase I)-Package 1 |
Nattika Project Dn |
|
2 |
Augmentation of CWSS to Nattika Firka( Phase I) - Package 2 |
Nattika Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
15 Feb 2024 |
Revised AS for Rs 88.78 crores received from KIIFB.TS obtained from CE, Package I Technical sanction confirmed From KIIFB and Package II have to submit for package approval |
Nattika Project Dn AE 6 |
|
14 Feb 2024 |
Revised AS for Rs 88.78 crores received from KIIFB.TS obtained from CE, Package I Technical sanction confirmed From KIIFB and Package II have to submit for package approval |
Nattika Project Dn AE 6 |
|
13 Feb 2024 |
Revised AS for Rs 88.78 crores received from KIIFB.TS obtained from CE, Package I Technical sanction confirmed From KIIFB and Package II have to submit for package approval |
Nattika Project Dn AE 6 |
|
12 Feb 2024 |
Revised AS for Rs 88.78 crores received from KIIFB.TS obtained from CE |
Nattika Project Dn AE 6 |
|
11 Feb 2024 |
Revised AS for Rs 88.78 crores received from KIIFB.TS obtained from CE |
Nattika Project Dn AE 6 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
25/02/2020 |
Scheduled date of Completion of the Project |
24 Feb 2022 |
Expected date of Completion |
31/03/2023 |
Processing Dates
AS Date |
19 Nov 2018 |
TS Date |
23 Sep 2019 |