RKI- Automation of submersible pumps in Kerala Water Authority- Implementation of Phase 1 (Stage 1 & 2), part under Rebuild Kerala Initiative - Karunagappally Municipality and Alappad & Kulasekharapuram Grama Panchayats.

Project RKI- Automation of submersible pumps in Kerala Water Authority- Implementation of Phase 1 (Stage 1 & 2), part under Rebuild Kerala Initiative - Karunagappally Municipality and Alappad & Kulasekharapuram Grama Panchayats.
Project Code KLMRKI032211981
Type Main project
Funding Agency RKI
Category RKI
Type of scheme Water Supply
Scheme 5475-00-115-94-05
Description Automation of submersible pumps in Kerala Water Authority- Implementation of Phase 1 (Stage 1 & 2), part under Rebuild Kerala Initiative - Karunagappally Municipality and Alappad & Kulasekharapuram Grama Panchayats.
Status Completed
District Kollam
Executing Office Oachira PH Sn
AS Amount (Rs) 200000
AS Number 6296/AE1(OPERATIONS)/2022/KWA
TS Amount (Rs) 120000
TS Number TS/2022-2023/2022/12499
Total Bill Submitted (Rs) 1
Total Bill Paid (Rs) 1
Population Benefitted 270000
Capacity in MLD 1.50
Actual Project Completion Date Date is not specified
Coverage Karunagappally,Alappad and KSpuram

Packages

No. Project Name Location View
1 RKI- Automation of submersible pumps in Kerala Water Authority- Implementation of Phase 1 (Stage 1 & 2), part under Rebuild Kerala Initiative - Karunagappally Municipality and Alappad & Kulasekharapuram Grama Panchayats. Oachira PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 Dec 2022 work completed Oachira AE
16 Dec 2022 work completed Oachira AE
13 Dec 2022 work completed Oachira AE
01 Nov 2022 work completed Chavara AEE
25 Oct 2022 work completed Oachira AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 02/08/2022
Scheduled date of Completion of the Project 01 Sep 2022
Expected date of Completion 01/09/2022

Processing Dates

AS Date 15 Mar 2022
TS Date 07 May 2022

Other details