- Home
- RKI- Automation of submersible pumps in...
RKI- Automation of submersible pumps in Kerala Water Authority- Implementation of Phase 1 (Stage 1 & 2), part under Rebuild Kerala Initiative - Karunagappally Municipality and Alappad & Kulasekharapuram Grama Panchayats.
Project |
RKI- Automation of submersible pumps in Kerala Water Authority- Implementation of Phase 1 (Stage 1 & 2), part under Rebuild Kerala Initiative - Karunagappally Municipality and Alappad & Kulasekharapuram Grama Panchayats. |
Project Code |
KLMRKI032211981 |
Type |
Main project |
Funding Agency |
RKI |
Category |
RKI |
Type of scheme |
Water Supply |
Scheme |
5475-00-115-94-05 |
Description |
Automation of submersible pumps in Kerala Water Authority- Implementation of Phase 1 (Stage 1 & 2), part under Rebuild Kerala Initiative - Karunagappally Municipality and Alappad & Kulasekharapuram Grama Panchayats. |
Status |
Completed |
District |
Kollam |
Executing Office |
Oachira PH Sn |
AS Amount (Rs) |
200000
|
AS Number |
6296/AE1(OPERATIONS)/2022/KWA |
TS Amount (Rs) |
120000 |
TS Number |
TS/2022-2023/2022/12499 |
Total Bill Submitted (Rs) |
1 |
Total Bill Paid (Rs) |
1 |
Population Benefitted |
270000 |
Capacity in MLD |
1.50 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Karunagappally,Alappad and KSpuram |
Packages
No. |
Project Name |
Location |
View |
1 |
RKI- Automation of submersible pumps in Kerala Water Authority- Implementation of Phase 1 (Stage 1 & 2), part under Rebuild Kerala Initiative - Karunagappally Municipality and Alappad & Kulasekharapuram Grama Panchayats. |
Oachira PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
17 Dec 2022 |
work completed |
Oachira AE |
|
16 Dec 2022 |
work completed |
Oachira AE |
|
13 Dec 2022 |
work completed |
Oachira AE |
|
01 Nov 2022 |
work completed |
Chavara AEE |
|
25 Oct 2022 |
work completed |
Oachira AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
02/08/2022 |
Scheduled date of Completion of the Project |
01 Sep 2022 |
Expected date of Completion |
01/09/2022 |
Processing Dates
AS Date |
15 Mar 2022 |
TS Date |
07 May 2022 |