| Project | JEL JEEVAN MISSION 2020-2021 PHASE 1 : Providing FHTC by Retrofitting and Extension from the ongoing water supply scheme WSS to Kunnummal Grama panchayath. |
|---|---|
| Project Code | CLTJJM08203635P1 |
| Type | Package |
| Main Project | JJM-Phase1- Kunnummal GP-Providing FHTC's by retofitting and extension |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Providing 2500 FHTC to Kunnummal Grama Panchayath. |
| Status | Completed |
| District | Kozhikkode |
| Executing Office | Kozhikode Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 66100000 |
| TS Number | TS/2020-2021/14022 |
| Technical specification | FHTC -2500 nos 90mm PVC Pipe 15250 m |
| Contractor | M/S Parambi Constructions (Mob: 9446504284) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 09/12/2020 |
|---|---|
| Scheduled date of Completion as per agreement | 05 May 2021 |
| Expected date of Completion | 04/05/2022 |
| TS Date | 27 Aug 2020 |
|---|---|
| Estimate Approval | 28 Aug 2020 |
| NIT Approval | 31 Aug 2020 |
| Tender Closing | 07 Dec 2020 |
| Technichal Pre-Qualification | 21 Aug 2020 |
| Price bid opening | 21 Aug 2020 |
| Workorder Date | 06 Nov 2020 |
|---|---|
| NA | 09 Dec 2020 |
| Kozhikode Project Dn AE5 |
| Date: 27/10/2022 |
Work has been completed | 100% Completed
Kunnummal grama panchayath is declared as an Har Gar Jal Panchayth (HGL) on 27.10.2022. Work completed, 2747 connections provided..
| Kozhikode Project Dn AE5 |
| Date: 05/05/2022 |
Work has been completed | 100% Completed
Work completed, 2747 connections provided. .