Drinking water supply scheme to Central University,Periya in Kasaragod District
Project |
Drinking water supply scheme to Central University,Periya in Kasaragod District |
Project Code |
KGDGOK0916685 |
Type |
Main project |
Funding Agency |
GOK |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
Construction of 4 MLD water treatment plant,Laying raw water pumping main-250mm Dia-6900meters,Intake well cum pump house 8.00m dia ,supply and erection of raw water pump sets 60 HP and power connection |
Status |
Completed |
District |
Kasaragod |
Executing Office |
Project Division Kannur ( KGD) |
AS Amount (Rs) |
105000000
|
AS Number |
GO(Rt)No. 2514/2016/HEDN of Higher Education Dept. |
TS Amount (Rs) |
|
TS Number |
KWA/CE/NR/11/2017-18 |
Total Bill Submitted (Rs) |
88691956 |
Total Bill Paid (Rs) |
88691956 |
Population Benefitted |
4000 |
Capacity in MLD |
4.00 |
Actual Project Completion Date |
05 Jun 2020 |
Coverage |
to benefit the Central University campus, Periya |
Packages
No. |
Project Name |
Location |
View |
1 |
Construction of 4MLD WTP,Intake well pump house,approach road, Supply and Laying pumping main and supply and erection of pump sets |
Project Division Kannur ( KGD) |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
13 Aug 2020 |
Work completed - 05-06-2020 |
Kanhangad Proj Dn AEE - 1 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
30/06/2018 |
Scheduled date of Completion of the Project |
05 Dec 2019 |
Expected date of Completion |
05/06/2020 |
Processing Dates
AS Date |
22 Sep 2016 |
TS Date |
26 Jul 2017 |