JJM - Kaduthuruthy Panchayath - Balance work - Providing water connection at ward no : 16 & 19 of Kaduthuruthy Grama Panchayath
Project |
JJM - Kaduthuruthy Panchayath - Balance work - Providing water connection at ward no : 16 & 19 of Kaduthuruthy Grama Panchayath |
Project Code |
KTMJJM082014113 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM - Kaduthuruthy Panchayath - Balance work - Providing water connection at ward no : 16 & 19 of Kaduthuruthy Grama Panchayath |
Status |
Completed |
District |
Kottayam |
Executing Office |
Kottayam PH Sn |
AS Amount (Rs) |
103600
|
AS Number |
G.O.(Rt)No.541/2020/WRD |
TS Amount (Rs) |
103600 |
TS Number |
TS/1417/2023-26-1-1 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
103600 |
Population Benefitted |
6 |
Capacity in MLD |
45.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
This estiamte is prepered for providing water connection to 6 numbers of houses in ward 16 and 1 number of house in ward 19 of Kaduthuruthy Panchayath. |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM - Kaduthuruthy Panchayath - Balance work - Providing water connection at ward no : 16 & 19 of Kaduthuruthy Grama Panchayath |
Kottayam PH Sn |
|
No status have been added to this project
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
27/03/2023 |
Scheduled date of Completion of the Project |
26 Apr 2023 |
Expected date of Completion |
26/04/2023 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
24 Jan 2023 |