JAL JEEVAN MISSION-Phase 1- 2020-21- Providing house connections in Alayamon panchayath of Kollam district
Project |
JAL JEEVAN MISSION-Phase 1- 2020-21- Providing house connections in Alayamon panchayath of Kollam district |
Project Code |
KLMJJM08203187 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Providing house connections in Alayamon panchayath of Kollam district |
Status |
On-going |
District |
Kollam |
Executing Office |
Madathara Sn |
AS Amount (Rs) |
129900000
|
AS Number |
GO(Rt) No. 541/202/WRD |
TS Amount (Rs) |
99700000 |
TS Number |
TS/2020-2021/2020/16247 |
Total Bill Submitted (Rs) |
64702497 |
Total Bill Paid (Rs) |
63309081 |
Population Benefitted |
27000 |
Capacity in MLD |
10.53 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Alayamon panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JAL JEEVAN MISSION -Pipe line extension & Providing house connections in Alayamon panchayath |
Madathara Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
27 Dec 2023 |
work complected |
Madathara PH Sn - AE |
|
30 Nov 2023 |
work complected |
Madathara PH Sn - AE |
|
12 Oct 2023 |
Road restoration works in progress. |
Madathara PH Sn - AE |
|
21 Aug 2023 |
House connections work, Pipe line extension and road restoration works in progress. |
Madathara PH Sn - AE |
|
06 Jul 2023 |
Pipe line extension and road restoration works in progress. |
Madathara PH Sn - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
08/03/2021 |
Scheduled date of Completion of the Project |
31 Mar 2022 |
Expected date of Completion |
31/05/2022 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
03 Sep 2020 |