Project | PACKAGE II- CONSTRUCTION OF 32 MLD CAPACITY WTP AT EDAKKANAM |
---|---|
Project Code | KNRJJM022213306P2 |
Type | Package |
Main Project | JJM-KANNUR DISTRICT- WSS TO TRIPPANGOTTUR & ADJOINING PANCHAYATHS |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-01 |
Description | Construction of 32 mld capacity WTP , Reservoir and all allied works including landscaping compound wall etc |
Status | On-going |
District | Kannur |
Executing Office | Mattannur Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 5320 |
TS Number | 10656/2023-2024 |
Technical specification | Construction , testing and commissioning of 32 mld WTP at Edakkanam and all allied works |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 30/08/2023 |
---|---|
Scheduled date of Completion as per agreement | 22 Feb 2025 |
Expected date of Completion | 31/12/2024 |
TS Date | 01 Aug 2023 |
---|---|
Estimate Approval | 01 Aug 2023 |
NIT Approval | 12 Aug 2023 |
Tender Closing | 31 Aug 2023 |
Technichal Pre-Qualification | 12 Aug 2023 |
Price bid opening | 01 Sep 2023 |
Workorder Date | 23 Sep 2023 |
---|---|
NA | 13 Nov 2023 |
Mattannur Project Sn 2 AE |
Date: 12/05/2025 |
Work in progress | 1% Completed
Earth excavation and site leveling work completed(initial stage) for clarifier completed. Soil testing and investigation study completed. report received.
Mattannur Project Sn 2 AE |
Date: 03/05/2025 |
Work in progress | 1% Completed
Earth excavation and site leveling work completed(initial stage) for clarifier completed. Soil testing and investigation study completed. report received.