- Home
- Jal Jeevan Mission (JJM)-Laying 90mm pvc...
Jal Jeevan Mission (JJM)-Laying 90mm pvc pipe and providing FHTCs in Puzhakkal Manidam road in connection withPMGSY Drainage and road work -Adat panchayath-Pipeline Work
Project |
Jal Jeevan Mission (JJM)-Laying 90mm pvc pipe and providing FHTCs in Puzhakkal Manidam road in connection withPMGSY Drainage and road work -Adat panchayath-Pipeline Work |
Project Code |
TCRJJM082012145 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Laying 90mm pvc pipe and providing FHTCs in Puzhakkal Manidam road in connection with PMGSY Drainage and road work -Adat panchayath-Pipeline Work |
Status |
Completed |
District |
Thrissur |
Executing Office |
Thrissur WW Sn 2 |
AS Amount (Rs) |
2593200000
|
AS Number |
G.O.(Rt)No.54 1/2 020/WRD |
TS Amount (Rs) |
7120000 |
TS Number |
WRD/KWA-CE(CR)/EST_TS/638/2022_26_1 |
Total Bill Submitted (Rs) |
1 |
Total Bill Paid (Rs) |
1 |
Population Benefitted |
4172 |
Capacity in MLD |
0.04 |
Actual Project Completion Date |
10 Sep 2022 |
Coverage |
Puzhakkal Manidam Road |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM)-Laying 90mm pvc pipe and providing FHTCs in Puzhakkal Manidam road in connection withPMGSY Drainage and road work -Adat panchayath-Pipeline Work |
Thrissur WW Sn 2 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
12 Feb 2024 |
Bill submitted
|
Thrissur WW Sn - AE 2 |
|
08 Feb 2024 |
Bill submitted |
Thrissur WW Sn - AE 2 |
|
01 Feb 2024 |
Bill submitted
|
Thrissur WW Sn - AE 2 |
|
20 Mar 2023 |
Work completed. Bill Submitted. |
Thrissur WW Sn - AE 2 |
|
16 Mar 2023 |
90mm PVC pipe line work is completed. |
Thrissur WW Sn - AE 2 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
12/08/2022 |
Scheduled date of Completion of the Project |
11 Sep 2022 |
Expected date of Completion |
31/05/2023 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
21 Jul 2022 |