- Home
- PROJECTS UNDER KERALA INFRA.INVT. FUND B...
PROJECTS UNDER KERALA INFRA.INVT. FUND BOARD KIIFB(74)--WSS to Kalluvathukkal Parippallay and Velinalloor(Part) Villages-Phase I (7520)
Project |
PROJECTS UNDER KERALA INFRA.INVT. FUND BOARD KIIFB(74)--WSS to Kalluvathukkal Parippallay and Velinalloor(Part) Villages-Phase I (7520) |
Project Code |
KLMKIIFB0117468 |
Type |
Main project |
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
KIIFB-WSS to Kalluvathukkal Parippallay and Velinalloor(Part) Villages-Phase I |
Status |
On-going |
District |
Kollam |
Executing Office |
Kollam Project Dn |
AS Amount (Rs) |
270000000
|
AS Number |
14/2017 |
TS Amount (Rs) |
270000000 |
TS Number |
26/2016-17 |
Total Bill Submitted (Rs) |
187974281 |
Total Bill Paid (Rs) |
187974281 |
Population Benefitted |
42929 |
Capacity in MLD |
7.50 |
Actual Project Completion Date |
12 Mar 2022 |
Coverage |
68347 |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
PACKAGE I-Design & construction of 6m dia. Intake well cum pump house.Supplying, laying, Commissioning and maintaining 400mm DI K9 RWPM from Intake well to WTP.Supply, Erection and Commissioning of 3 Nos. of 110HP VT Raw Water Pump sets, Electrical substation,erection of 400KVA USS indoor transformer and allied works. |
Kollam Project Dn |
|
2 |
"PACKAGE II-Design, Construction and commissioning of 7.5 MLD conventional type rapid sand filter Water Treatment Plant (WTP) including 4.50 LL CW sump Construction of 9.0 Lakhs Litrecapacity OHSR at Kattupuram, Supply, Erection and Commissioning of Clear Water Pump sets , Supplying Laying and commissioning of 350mm DI K9 Clear Water Pumping Main" |
Kollam Project Dn |
|
3 |
PACKAGE III-Construction of new weir at Mannayam, about three KMs upstream side of the Aduthala bridge. |
Kollam Project Dn |
|
4 |
PACKAGE IV-Rehabilitation of existing 1.5 MLD (slow sand filter)Treatment plant at Velinalloor |
Kollam Project Dn |
|
5 |
PACKAGE VI- Providing scour line from WTP to mannayam bridge, Providing RR masonry at well site as protection works , providing interlock in approach road and construction of washroom at well site for operators. -General Civil Work |
Kollam Project Dn |
|
6 |
PACKAGE V-Strengthening of the existing weir constructed by the Irrigation department at Aduthala and its allied works |
Kollam Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
14 Nov 2023 |
Out of 6 packages, 3 nos completed.. Packages 3 for construction of weir is in progress. Packages 5 for reformation of weir is temporarily stopped due to high water table. Packages 6 for Constrution of retaining wall and laying of scour line from WTP are in progress. |
Kollam Project HD |
|
15 Jun 2023 |
One new package were added. Out of 6 packages, 3 nos completed.. Packages 3 for construction of weir is in progress. Packages 5 for reformation of weir is temporarily stopped due to high water table. Packages 6 for Constrution of retaining wall and laying of scour line from WTP are in progress. |
Kollam Project HD |
|
03 Apr 2023 |
Out of 5 packages, 2 nos completed. Package 2 99% completed except NHAI crossing at Kalluvathukkal Jn which is scheduled to start on 05.04.2023. Packages 3 & 5 for construction and reformation of weirs are in progress. |
Kollam Project Dn EE |
|
11 Jun 2022 |
NHAI deputy manager (Technical )visited Kalluvathukkal crossing point with KWA officials and NHAI Contractors representatives for ensuring Technical feasibility of crossing on 10.06.2022 |
Kollam Project HD |
|
26 May 2022 |
NHAI representative assured to accord sanction for NH 66 crossing at Kalluvathukkal junction within one week in Road coordination committee held in the chamber of Hon District Collector Kollam on 26-05-22 |
Kollam Project HD |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
04/03/2018 |
Scheduled date of Completion of the Project |
12 Mar 2022 |
Expected date of Completion |
30/09/2023 |
Processing Dates
AS Date |
11 Jan 2017 |
TS Date |
24 Mar 2017 |