Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

AMRUT 2.0 UWSS to Alappuzha Municipality -WSS to Alappuzha municipality Providing Standby raw water and clear water pump sets, Flow Meter and General Maintenance works of WTP at Karumady

Project AMRUT 2.0 UWSS to Alappuzha Municipality -WSS to Alappuzha municipality Providing Standby raw water and clear water pump sets, Flow Meter and General Maintenance works of WTP at Karumady
Project Code ALPAMRUT112213107P2
Type Package
Main Project Amrut 2.0-UWSS to Alappuzha Municipality
Funding Agency AMRUT 2
Category AMRUT
Type of scheme Water Supply
Scheme
Description supply and erection of raw water and clear water pump sets at intake well at Kadapra and WTP, Karumady respectively and supply & erection of flow meter in raw water pumping main at Kadapra and other general maintenance works of the 62MLD WTP at Karumady
Status On-going
District Alappuzha
Executing Office Alappuzha Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 17610000
TS Number WRD/KWA-CE(CR)/EST_TS/4928/2022_5_1_1
Technical specification 360 HP Centrifugal pump set Clear water Pump at , Karumadi WTP (51 m Head)- 1 no 240 HP Centrifugal pump at Raw water pump at Kadapra (38 m Head) -1 no Ultrasonic flow metre - 1 no

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion Date is not specified

Processing Dates

TS Date 16 Jun 2023
Estimate Approval 16 Jun 2023
NIT Approval 18 Jan 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Alappuzha Project Dn PM
Date: 17/05/2024

Work has started | 0% Completed

Soil investigation completed and results received and design of pump house extension is ongoing. The contractor submitted QAP Documents for the approval of pumps and approved. Accordingly, the Contractor placed the order for procurement of pumps. .

Alappuzha Project Dn PM
Date: 16/05/2024

Work has started | 0% Completed

Soil investigation completed and results received and design of pump house extension is ongoing. The contractor submitted QAP Documents for the approval of pumps and approved. Accordingly, the Contractor placed the order for procurement of pumps. .