- Home
- Deposit WorkRWSS To Sooranadu North - In...
Deposit WorkRWSS To Sooranadu North - Interconnection of newly laid 63 mm PVC pipe line with existing main line and fixing valve at East High School Junction near Puthiyakavu temple, Ward No.X of Sooranadu North Grama Panchayath
Project |
Deposit WorkRWSS To Sooranadu North - Interconnection of newly laid 63 mm PVC pipe line with existing main line and fixing valve at East High School Junction near Puthiyakavu temple, Ward No.X of Sooranadu North Grama Panchayath |
Project Code |
KLMDEPO022212402 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
RWSS To Sooranadu North - Interconnection of newly laid 63 mm PVC pipe line with existing main line and fixing valve at East High School Junction near Puthiyakavu temple, Ward No.X of Sooranadu North Grama Panchayath |
Status |
Completed |
District |
Kollam |
Executing Office |
Kollam PH Sub Dn |
AS Amount (Rs) |
28900
|
AS Number |
S3-6189/21 |
TS Amount (Rs) |
28900 |
TS Number |
TS/2021-2022/2020/25873 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
100 |
Capacity in MLD |
0.14 |
Actual Project Completion Date |
26 Oct 2022 |
Coverage |
100 families of Sooranadu North GP |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit Work - RWSS To Sooranadu North - Interconnection of newly laid 63 mm PVC pipe line with existing main line and fixing valve at East High School Junction near Puthiyakavu temple, Ward No.X of Sooranadu North Grama Panchayath |
Kollam PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
23 Nov 2022 |
Interconnection of newly laid 63 mm PVC pipe line with existing main line at East High School Junction near Puthiyakavu temple, Ward No.X of Sooranadu North Grama Panchayath - work 100% completed |
Sasthamcotta WS Sn 1 - AE |
|
22 Nov 2022 |
Laying of 63 mm PVC pipe work on progress |
Sasthamcotta WS Sn 1 - AE |
|
21 Nov 2022 |
Laying of 63 mm PVC pipe 15 m completed. Balance work on progress |
Sasthamcotta WS Sn 1 - AE |
|
16 Nov 2022 |
Work started on 16.11.2022 |
Sasthamcotta WS Sn 1 - AE |
|
14 Nov 2022 |
Road cutting sanction is required, demand notice has been forwarded for the remittance of payment |
Sasthamcotta WS Sn 1 - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
02/02/2022 |
Scheduled date of Completion of the Project |
26 Oct 2022 |
Expected date of Completion |
26/10/2022 |
Processing Dates
AS Date |
02 Feb 2022 |
TS Date |
26 Feb 2022 |