Project | State plan 2023-24 Optimization of production and transmission- Pipe line replacement- Relaying of frequently breaking PVC pipe line from Pulivalam to Santhwanam School road in Balussery Panchayath |
---|---|
Project Code | CLTGOK072314524P1 |
Type | Package |
Main Project | State plan 2023-24 Optimization of production and transmission- Pipe line replacement- Relaying of frequently breaking PVC pipe line from Pulivalam to Santhwanam School road in Balussery Panchayath |
Funding Agency | GOK |
Category | State plan |
Type of scheme | Water Supply |
Scheme | 4215-01-800-87 |
Description | State plan 2023-24 Optimization of production and transmission- Pipe line replacement- Relaying of frequently breaking PVC pipe line from Pulivalam to Santhwanam School road in Balussery Panchayath |
Status | On-going |
District | Kozhikkode |
Executing Office | Koyilandy PH Sn 1 |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 4300000 |
TS Number | 11001/2023-24 |
Technical specification | Pipe line replacement |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 24/09/2023 |
---|---|
Scheduled date of Completion as per agreement | 23 Dec 2023 |
Expected date of Completion | 31/03/2024 |
TS Date | 03 Aug 2023 |
---|---|
Estimate Approval | 03 Aug 2023 |
Workorder Date | 08 Sep 2023 |
---|---|
NA | 14 Sep 2023 |
Koyilandy PH Section 1 - AE |
Date: 23/04/2024 |
Work has been completed | 100% Completed
Work Completed..
Koyilandy PH Sub Dn - AEE |
Date: 06/03/2024 |
Work in progress | 90% Completed
All works completed except Road Restoration.