Deposit work-2022-23-CWSS to Vithura and Tholicode villages (Annual scheme-2022-23)-Pipe line extensions of various stretches in Vithura Grama Panchayath (1) Koppam Jn-Taluk Hospital road (2) Darpa-Vavupura road (3) Chayam Aalaivilakom Sasthamkavu Pannikonam bhagam ward 2 (4) Ponnamchund Jn-Charuvila Erachippara road (5) Kallar 3 cent colony mammood bhagam-Narakathinkala (6) Valenki-Karikkunnu road ward 6 (7) Mullachira- Kochumullachira bhagam of ward no.9 (8) Kochukilikoodu-Ottakkudi-Meenankal bhagam (9) KPSM-Church to Pottikkunnu ward-15 at Vithura grama panchayath-Pipe line work.
Project |
Deposit work-2022-23-CWSS to Vithura and Tholicode villages (Annual scheme-2022-23)-Pipe line extensions of various stretches in Vithura Grama Panchayath (1) Koppam Jn-Taluk Hospital road (2) Darpa-Vavupura road (3) Chayam Aalaivilakom Sasthamkavu Pannikonam bhagam ward 2 (4) Ponnamchund Jn-Charuvila Erachippara road (5) Kallar 3 cent colony mammood bhagam-Narakathinkala (6) Valenki-Karikkunnu road ward 6 (7) Mullachira- Kochumullachira bhagam of ward no.9 (8) Kochukilikoodu-Ottakkudi-Meenankal bhagam (9) KPSM-Church to Pottikkunnu ward-15 at Vithura grama panchayath-Pipe line work. |
Project Code |
TVMDEPO032214295 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit work-2022-23-CWSS to Vithura and Tholicode villages (Annual scheme-2022-23)-Pipe line extensions of various stretches in Vithura Grama Panchayath (1) Koppam Jn-Taluk Hospital road (2) Darpa-Vavupura road (3) Chayam Aalaivilakom Sasthamkavu Pannikonam bhagam ward 2 (4) Ponnamchund Jn-Charuvila Erachippara road (5) Kallar 3 cent colony mammood bhagam-Narakathinkala (6) Valenki-Karikkunnu road ward 6 (7) Mullachira- Kochumullachira bhagam of ward no.9 (8) Kochukilikoodu-Ottakkudi-Meenankal bhagam (9) KPSM-Church to Pottikkunnu ward-15 at Vithura grama panchayath-Pipe line work. |
Status |
Completed |
District |
Thiruvananthapuram |
Executing Office |
Aruvikkara HW Dn |
AS Amount (Rs) |
3330646
|
AS Number |
GO(Rt)No.489/2021/Fin |
TS Amount (Rs) |
3329720 |
TS Number |
3344/2023-2024 |
Total Bill Submitted (Rs) |
2314780 |
Total Bill Paid (Rs) |
2314780 |
Population Benefitted |
400 |
Capacity in MLD |
0.02 |
Actual Project Completion Date |
01 Sep 2023 |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work-2022-23-CWSS to Vithura and Tholicode villages (Annual scheme-2022-23)-Pipe line extensions of various stretches in Vithura Grama Panchayath (1) Koppam Jn-Taluk Hospital road (2) Darpa-Vavupura road (3) Chayam Aalaivilakom Sasthamkavu Pannikonam bhagam ward 2 (4) Ponnamchund Jn-Charuvila Erachippara road (5) Kallar 3 cent colony mammood bhagam-Narakathinkala (6) Valenki-Karikkunnu road ward 6 (7) Mullachira- Kochumullachira bhagam of ward no.9 (8) Kochukilikoodu-Ottakkudi-Meenankal bhagam (9) KPSM-Church to Pottikkunnu ward-15 at Vithura grama panchayath-Pipe line work. |
Palod WS Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
25 Oct 2023 |
Work Completed.Bill Submitted |
Palode AE |
|
11 Sep 2023 |
Work Completed.Bill Submitted |
Palode AE |
|
07 Sep 2023 |
Work Completed.Bill Submitted |
Palode AE |
|
04 Sep 2023 |
Work Completed.Bill Under Preparation |
Palode AE |
|
02 Sep 2023 |
Work Completed.Bill Under Preparation |
Palode AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
30/05/2023 |
Scheduled date of Completion of the Project |
29 Sep 2023 |
Expected date of Completion |
29/09/2023 |
Processing Dates
AS Date |
16 Mar 2021 |
TS Date |
17 May 2023 |