DEPOSIT-Smart City-Smart city Thiruvananthapuram Ltd - Reconstruction / maintenance of sewerage system at Sreemoolam road (Road id - 90B) due to work carried out by Smart City

Project DEPOSIT-Smart City-Smart city Thiruvananthapuram Ltd - Reconstruction / maintenance of sewerage system at Sreemoolam road (Road id - 90B) due to work carried out by Smart City
Project Code TVMSMARTCITY042314429P1
Type Package
Main Project DEPOSIT-Smart City Smart city Thiruvananthapuram Ltd - Reconstruction / maintenance of sewerage system at Sreemoolam road (Road id - 90B) due to work carried out by Smart City
Funding Agency SMARTCITY
Category Deposit Work
Type of scheme Water Supply
Scheme Smart City
Description DEPOSIT-Smart City-Smart city Thiruvananthapuram Ltd - Reconstruction / maintenance of sewerage system at Sreemoolam road (Road id - 90B) due to work carried out by Smart City
Status On-going
District Thiruvananthapuram
Executing Office Kuriathy Sewerage Sn 2
Agreement Number
Agreement Date
TS Amount (Rs) 1871000
TS Number WRD/KWA-CE(SR)/EST_TS/2287/2023_27_1_1
Technical specification Pipe laying - 75 m

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 27/05/2023
Scheduled date of Completion as per agreement 26 Jul 2024
Expected date of Completion 26/03/2024

Processing Dates

TS Date 06 May 2023
Estimate Approval 06 May 2023
NIT Approval 06 May 2023
Tender Closing 16 May 2023
Technichal Pre-Qualification 16 May 2023
Price bid opening 20 May 2023

Approval Dates

Workorder Date 27 May 2023
NA 03 Jun 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kuriathy Sewerage Sn2 AE
Date: 01/12/2023

Work has been completed | 100% Completed

Work completed.

Kuriathy Sewerage Sn2 AE
Date: 17/08/2023

Work in progress | 95% Completed

Due to the presence of the electric cable SS covil road, the newly laid line is not able to connect with the existing MH in the SS covil road..