DEPOSIT-Kochi Corporation-Laying 63mm PVC pipe along Vattathippadam East road for improving water supply in Kochi Corporation division 32 (old) and 43(new)-Pipeline Work

Project DEPOSIT-Kochi Corporation-Laying 63mm PVC pipe along Vattathippadam East road for improving water supply in Kochi Corporation division 32 (old) and 43(new)-Pipeline Work
Project Code EKMDEPO062215424P1
Type Package
Main Project DEPOSIT-Kochi Corporation-Laying 63mm PVC pipe along Vattathippadam East road for improving water supply in Kochi Corporation division 32 (old) and 43(new)-Pipeline Work
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-Kochi Corporation-Laying 63mm PVC pipe along Vattathippadam East road for improving water supply in Kochi Corporation division 32 (old) and 43(new)-Pipeline Work
Status On-going
District Ernakulam
Executing Office Vytilla Section 1
Agreement Number
Agreement Date
TS Amount (Rs) 252000
TS Number WRD/KWA-CE(CR)/EST_TS/11073/2023_26_1_1
Technical specification DEPOSIT-Kochi Corporation-Laying 63mm PVC pipe along Vattathippadam East road for improving water supply in Kochi Corporation division 32 (old) and 43(new)-Pipeline Work
Contractor Biju T.R (Mob: 9349415119)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 08/01/2024
Scheduled date of Completion as per agreement 09 Mar 2024
Expected date of Completion 09/03/2024

Processing Dates

TS Date 15 Jun 2023
Estimate Approval 27 Feb 2023
Tender Closing 06 Jul 2023
Price bid opening 07 Jul 2023

Approval Dates

Workorder Date 22 Nov 2023
NA 02 Dec 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Vytilla Section AE - 1
Date: 15/02/2024

Work has been completed | 100% Completed

E bill submitted.

Vytilla Section AE - 1
Date: 14/02/2024

Work has been completed | 100% Completed

E bill submitted.