29-RWSS to Pullinkunnu - Providing water supply to Ambanappally SC colony in ward No.6 of Pullinkunnu Panchayath under water crossing with 110mm HDPE pipe at Korathara palam
Project |
29-RWSS to Pullinkunnu - Providing water supply to Ambanappally SC colony in ward No.6 of Pullinkunnu Panchayath under water crossing with 110mm HDPE pipe at Korathara palam |
Project Code |
ALPGOK12141969 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
Replacing of Pipe line |
Status |
Completed |
District |
Alappuzha |
Executing Office |
Thiruvalla PH Dn |
AS Amount (Rs) |
500000
|
AS Number |
KWA/JB/P6M-1/905/2015-16 |
TS Amount (Rs) |
500000 |
TS Number |
8/15-16/EE/PHDN/TVLA |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
100 |
Capacity in MLD |
0.10 |
Actual Project Completion Date |
10 Feb 2021 |
Coverage |
Ambanappally |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
29-RWSS to Pullinkunnu - Providing water supply to Ambanappally SC colony in ward No.6 of Pullinkunnu Panchayath under water crossing with 110mm HDPE pipe at Korathara palam |
Thiruvalla PH Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
26 Oct 2021 |
bill under prepared |
Thiruvalla PH Dn EE |
|
13 Sep 2021 |
bill under prepared |
Thiruvalla PH Dn EE |
|
10 Jun 2021 |
100% Completed |
Thiruvalla PH Dn EE |
|
11 Feb 2021 |
Completed |
Thiruvalla PH Dn EE |
|
03 Feb 2021 |
road cutting sanction tobe recieved |
Thiruvalla PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
30/01/2021 |
Scheduled date of Completion of the Project |
15 Feb 2021 |
Expected date of Completion |
10/02/2021 |
Processing Dates
AS Date |
23 Dec 2014 |
TS Date |
08 Dec 2015 |