State Plan (2018-2019 )- RWSS to Nooranad-Replacing of old damaged AC pipe line from Edapon towards Para Jn with 160 mm (6 kg/cm2 ) PVC pipe line

Project State Plan (2018-2019 )- RWSS to Nooranad-Replacing of old damaged AC pipe line from Edapon towards Para Jn with 160 mm (6 kg/cm2 ) PVC pipe line
Project Code ALPGOK04181399P1
Type Package
Main Project State Plan (2018-2019 )- RWSS to Nooranad-Replacing of old damaged AC pipe line from Edapon towards Para Jn with 160 mm (6 kg/cm2 ) PVC pipe line
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 4215-01-800-89
Description State Plan (2018-2019 )- RWSS to Nooranad-Replacing of old damaged AC pipe line from Edapon towards Para Jn with 160 mm (6 kg/cm2 ) PVC pipe line
Status On-going
District Alappuzha
Executing Office Mavelikkara WS Sn
Agreement Number
Agreement Date
TS Amount (Rs) 13100000
TS Number TS/2018-19/2018/3902
Technical specification Replacing of old damaged AC pipe line from Edapon towards Para Jn with 160 mm (6 kg/cm2 ) PVC pipe line

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 22/05/2019
Scheduled date of Completion as per agreement 25 Jul 2019
Expected date of Completion 15/02/2022

Processing Dates

TS Date 20 Dec 2018
Estimate Approval 20 Dec 2020
NIT Approval 20 Dec 2020
Tender Closing 25 Jan 2019
Technichal Pre-Qualification 25 Jan 2019
Price bid opening 30 Jan 2019

Approval Dates

Workorder Date 08 Feb 2019
NA 01 Mar 2019

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Alappuzha PH Dn EE
Date: 15/02/2022

Work has been completed | 100% Completed

Work Completed.

Alappuzha PH Dn EE
Date: 09/02/2022

Work in progress | 99% Completed

Work in progress.