| Project | State Plan (2018-2019 )- RWSS to Nooranad-Replacing of old damaged AC pipe line from Edapon towards Para Jn with 160 mm (6 kg/cm2 ) PVC pipe line |
|---|---|
| Project Code | ALPGOK04181399P1 |
| Type | Package |
| Main Project | State Plan (2018-2019 )- RWSS to Nooranad-Replacing of old damaged AC pipe line from Edapon towards Para Jn with 160 mm (6 kg/cm2 ) PVC pipe line |
| Funding Agency | GOK |
| Category | State plan |
| Type of scheme | Water Supply |
| Scheme | 4215-01-800-89 |
| Description | State Plan (2018-2019 )- RWSS to Nooranad-Replacing of old damaged AC pipe line from Edapon towards Para Jn with 160 mm (6 kg/cm2 ) PVC pipe line |
| Status | On-going |
| District | Alappuzha |
| Executing Office | Mavelikkara WS Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 13100000 |
| TS Number | TS/2018-19/2018/3902 |
| Technical specification | Replacing of old damaged AC pipe line from Edapon towards Para Jn with 160 mm (6 kg/cm2 ) PVC pipe line |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 22/05/2019 |
|---|---|
| Scheduled date of Completion as per agreement | 25 Jul 2019 |
| Expected date of Completion | 15/02/2022 |
| TS Date | 20 Dec 2018 |
|---|---|
| Estimate Approval | 20 Dec 2020 |
| NIT Approval | 20 Dec 2020 |
| Tender Closing | 25 Jan 2019 |
| Technichal Pre-Qualification | 25 Jan 2019 |
| Price bid opening | 30 Jan 2019 |
| Workorder Date | 08 Feb 2019 |
|---|---|
| NA | 01 Mar 2019 |
| Alappuzha PH Dn EE |
| Date: 15/02/2022 |
Work has been completed | 100% Completed
Work Completed.
| Alappuzha PH Dn EE |
| Date: 09/02/2022 |
Work in progress | 99% Completed
Work in progress.