| Project | NABARD-RIDF-XXII-WSS TO PATTUVAM AND ADJOINING VILLAGES (JICA AIDED) BALANCE DISTRIBUTION NETWORK - PHASE-I - APPENDIX-II- KALLIASSERY PANCHAYATH |
|---|---|
| Project Code | KNRNABARD1116740P2 |
| Type | Package |
| Main Project | NABARD-RIDF-XXII-WSS TO PATTUVAM AND ADJOINING VILLAGES (JICA AIDED) BALANCE DISTRIBUTION NETWORK - PHASE-I |
| Funding Agency | NABARD |
| Category | NABARD |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-98 (01) |
| Description | In this package, it is proposed to lay balance distribution network of WSS to Pattuvam(JICA) in Kalliassery Panchayath. This work has been completed |
| Status | On-going |
| District | Kannur |
| Executing Office | Thaliparambu WS Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | |
| TS Number | |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 13/03/2017 |
|---|---|
| Scheduled date of Completion as per agreement | Date is not specified |
| Expected date of Completion | 31/05/2018 |
| AS Date | 16 Nov 2016 |
|---|---|
| TS Date | 05 Dec 2016 |
| Estimate Approval | 10 Jan 2017 |
| Workorder Date | 18 Mar 2017 |
|---|---|
| NA | 04 Apr 2017 |
| Thaliparamba WS Dn EE |
| Date: 31/07/2020 |
Work has been completed | 100% Completed
work has been completed.