DEOPIST WORK- 2019-2020 Extension of pipeline in various wards 1,2,4,5,6,7,8,9,10,12,13,14,16 of sreemoolangaram panchayath
Project |
DEOPIST WORK- 2019-2020 Extension of pipeline in various wards 1,2,4,5,6,7,8,9,10,12,13,14,16 of sreemoolangaram panchayath |
Project Code |
EKMDEPO08207891P1 |
Type |
Package |
Main Project |
DEOPIST WORK- 2019-2020 Extension of pipeline in various wards 1,2,4,5,6,7,8,9,10,12,13,14,16 of sreemoolangaram panchayath
|
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
DEOPIST WORK- 2019-2020 Extension of pipeline in various wards 1,2,4,5,6,7,8,9,10,12,13,14,16 of sreemoolangaram panchayath |
Status |
Completed |
District |
Ernakulam |
Executing Office |
Chowara HW Sn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
766000 |
TS Number |
007961 |
Technical specification |
pipe line extension |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
08/10/2020 |
Scheduled date of Completion as per agreement |
07 Jan 2021 |
Expected date of Completion |
07/01/2021 |
Processing Dates
TS Date |
24 Aug 2020 |
Estimate Approval |
24 Aug 2020 |
NIT Approval |
27 Aug 2020 |
Tender Closing |
11 Sep 2020 |
Technichal Pre-Qualification |
24 Aug 2020 |
Price bid opening |
15 Sep 2020 |
Approval Dates
Workorder Date |
08 Oct 2020 |
NA |
12 Oct 2020 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Angamaly AEE |
Date: 27/08/2021 |
Work has been completed | 100% Completed
Work completed..
Angamaly AEE |
Date: 24/08/2021 |
Work in progress | 94% Completed
94% completed..