Augmentation of water supply scheme to Thripunithura municipality &adjoining panchayath - Supply erection testing and commissioning of 3 nos. Centrifugal pump sets with a discharge of 278 lps against a total head of 59 m with a minimum efficiency of 70% at CWPH Choondy

Project Augmentation of water supply scheme to Thripunithura municipality &adjoining panchayath - Supply erection testing and commissioning of 3 nos. Centrifugal pump sets with a discharge of 278 lps against a total head of 59 m with a minimum efficiency of 70% at CWPH Choondy
Project Code EKMGOK10145100P4
Type Package
Main Project Augmentation of water supply scheme to Thripunithura municipality &adjoining panchayath
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description Augmentation of water supply scheme to Thripunithura municipality &adjoining panchayath - Supply erection testing and commissioning of 3 nos. Centrifugal pump sets with a discharge of 278 lps against a total head of 59 m with a minimum efficiency of 70% at CWPH Choondy
Status Completed
District Ernakulam
Executing Office Kochi WS Dn
Agreement Number
Agreement Date
TS Amount (Rs)
TS Number
Technical specification Supply erection testing and commissioning of 3 nos. Centrifugal pump sets with a discharge of 278 lps against a total head of 59 m with a minimum efficiency of 70% at CWPH Choondy

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 20/07/2016
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion 07/12/2019

Processing Dates

AS Date 15 Oct 2014
TS Date 22 Nov 2014
Estimate Approval 22 Nov 2014
Tender Closing 05 Nov 2015
Price bid opening 09 Nov 2015

Approval Dates

CE Approval 15 Jul 2016
Workorder Date 29 Jul 2016
NA 12 Aug 2016

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kochi WS Dn EE
Date: 23/11/2020

Work has been completed | 100% Completed