Project | Jal Jeevan Mission - Providing FHTCs by Augmentation of existing WSS at Chakkittapara Grama Panchayath, Muthukkad Zone -Supplying Laying Testing and Commissioning of CWGM/CWPM, Distribution lines in various Zones |
---|---|
Project Code | CLTJJM022213897P1 |
Type | Package |
Main Project | Jal Jeevan Mission - Providing FHTCs by Augmentation of existing WSS at Chakkittapara Grama Panchayath, Muthukkad Zone -Supplying Laying Testing and Commissioning of CWGM/CWPM, Distribution lines in various Zones |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Supplying Laying Testing and Commissioning of CWGM/CWPM, Distribution lines in various Zones |
Status | On-going |
District | Kozhikkode |
Executing Office | Kozhikode Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 193100000 |
TS Number | WRD/KWA-CE(NR)/EST_TS/3448/2022_26_1_1 |
Technical specification | 1867 nos of FHTCs |
Contractor | Aboobacker SIDDIQUE (Mob: 9447010750) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 30/03/2023 |
---|---|
Scheduled date of Completion as per agreement | 21 Mar 2024 |
Expected date of Completion | 31/05/2024 |
TS Date | 02 Nov 2022 |
---|---|
Estimate Approval | 02 Nov 2022 |
Tender Closing | 10 Jan 2023 |
Technichal Pre-Qualification | 10 Mar 2023 |
Price bid opening | 11 Jan 2023 |
Workorder Date | 22 Mar 2023 |
---|---|
NA | 30 Mar 2023 |
Kozhikode Project Dn AE4 |
Date: 17/05/2024 |
Work in progress | 66% Completed
150mm DI-1518m, 200mm DI- 880m, 80mm GI - 8688m, 100mm GI -942m, 125mm GI -1776m, 90mm PE - 20647m, 110mm PE - 355m, 1215mm PE - 1008m, 140mm PE - 765m, 160mm PE - 1332m, 180mm PE - 252m supplied. 90mm PE -8254 m, 100mm GI- 1800m and 80mm GI - 7816m laid, Pipe laying work in progress. 325HTC provided. .
Kozhikode Project Dn AE4 |
Date: 16/05/2024 |
Work in progress | 66% Completed
150mm DI-1518m, 200mm DI- 880m, 80mm GI - 8688m, 100mm GI -942m, 125mm GI -1776m, 90mm PE - 20647m, 110mm PE - 355m, 1215mm PE - 1008m, 140mm PE - 765m, 160mm PE - 1332m, 180mm PE - 252m supplied. 90mm PE -8254 m, 100mm GI- 1800m and 80mm GI - 7816m laid, Pipe laying work in progress. 325HTC provided. .