Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan Mission - Providing FHTCs by Augmentation of existing WSS at Chakkittapara Grama Panchayath, Muthukkad Zone -Supplying Laying Testing and Commissioning of CWGM/CWPM, Distribution lines in various Zones

Project Jal Jeevan Mission - Providing FHTCs by Augmentation of existing WSS at Chakkittapara Grama Panchayath, Muthukkad Zone -Supplying Laying Testing and Commissioning of CWGM/CWPM, Distribution lines in various Zones
Project Code CLTJJM022213897P1
Type Package
Main Project Jal Jeevan Mission - Providing FHTCs by Augmentation of existing WSS at Chakkittapara Grama Panchayath, Muthukkad Zone -Supplying Laying Testing and Commissioning of CWGM/CWPM, Distribution lines in various Zones
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Supplying Laying Testing and Commissioning of CWGM/CWPM, Distribution lines in various Zones
Status On-going
District Kozhikkode
Executing Office Kozhikode Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 193100000
TS Number WRD/KWA-CE(NR)/EST_TS/3448/2022_26_1_1
Technical specification 1867 nos of FHTCs
Contractor Aboobacker SIDDIQUE (Mob: 9447010750)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 30/03/2023
Scheduled date of Completion as per agreement 21 Mar 2024
Expected date of Completion 31/05/2024

Processing Dates

TS Date 02 Nov 2022
Estimate Approval 02 Nov 2022
Tender Closing 10 Jan 2023
Technichal Pre-Qualification 10 Mar 2023
Price bid opening 11 Jan 2023

Approval Dates

Workorder Date 22 Mar 2023
NA 30 Mar 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kozhikode Project Dn AE4
Date: 17/05/2024

Work in progress | 66% Completed

150mm DI-1518m, 200mm DI- 880m, 80mm GI - 8688m, 100mm GI -942m, 125mm GI -1776m, 90mm PE - 20647m, 110mm PE - 355m, 1215mm PE - 1008m, 140mm PE - 765m, 160mm PE - 1332m, 180mm PE - 252m supplied. 90mm PE -8254 m, 100mm GI- 1800m and 80mm GI - 7816m laid, Pipe laying work in progress. 325HTC provided. .

Kozhikode Project Dn AE4
Date: 16/05/2024

Work in progress | 66% Completed

150mm DI-1518m, 200mm DI- 880m, 80mm GI - 8688m, 100mm GI -942m, 125mm GI -1776m, 90mm PE - 20647m, 110mm PE - 355m, 1215mm PE - 1008m, 140mm PE - 765m, 160mm PE - 1332m, 180mm PE - 252m supplied. 90mm PE -8254 m, 100mm GI- 1800m and 80mm GI - 7816m laid, Pipe laying work in progress. 325HTC provided. .