- Home
- DEPOSIT-Deposit work -Kadambur Grama Pan...
DEPOSIT-Deposit work -Kadambur Grama Panchayath-W.S.S to Anjarakandy, Peralassery and adjoining pt.-Public tap disconnection in Kadambur Panchayath-Pipeline Work
| Project |
DEPOSIT-Deposit work -Kadambur Grama Panchayath-W.S.S to Anjarakandy, Peralassery and adjoining pt.-Public tap disconnection in Kadambur Panchayath-Pipeline Work |
| Project Code |
KNRDEPO072314805 |
| Type |
Main project |
| Funding Agency |
DEPO |
| Category |
Deposit Work |
| Type of scheme |
Water Supply |
| Scheme |
DEPO |
| Description |
DEPOSIT-Deposit work -Kadambur Grama Panchayath-W.S.S to Anjarakandy, Peralassery and adjoining pt.-Public tap disconnection in Kadambur Panchayath-Pipeline Work |
| Status |
Completed |
| District |
Kannur |
| Executing Office |
Perlassery Sn 2 |
| AS Amount (Rs) |
120000
|
| AS Number |
01059/GADC01/GPO/2023/2996(1) |
| TS Amount (Rs) |
120000 |
| TS Number |
10795/2023-2024 |
| Total Bill Submitted (Rs) |
|
| Total Bill Paid (Rs) |
|
| Population Benefitted |
|
| Capacity in MLD |
46.00 |
| Actual Project Completion Date |
20 Feb 2024 |
| Coverage |
|
Packages
| No. |
Project Name |
Location |
View |
| 1 |
DEPOSIT-Deposit work -Kadambur Grama Panchayath-W.S.S to Anjarakandy, Peralassery and adjoining pt.-Public tap disconnection in Kadambur Panchayath-Pipeline Work |
Perlassery Sn 2 |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 08 Oct 2024 |
work completed |
Perlassery Sn 2 AE |
|
| 04 Oct 2024 |
work in progress |
Perlassery Sn 2 AE |
|
| 30 Sep 2024 |
work in progress |
Perlassery Sn 2 AE |
|
| 23 Sep 2024 |
work in progress |
Perlassery Sn 2 AE |
|
| 18 Sep 2024 |
work in progress |
Perlassery Sn 2 AE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
02/08/2023 |
| Scheduled date of Completion of the Project |
31 Oct 2023 |
| Expected date of Completion |
31/10/2023 |
Processing Dates
| AS Date |
11 Jul 2023 |
| TS Date |
02 Aug 2023 |