State Plan – 2023-24- Optimisation of production and transmission – Energy Conservation – Supply, Fixing and Commissioning of 845 HP VT pumpset in intake well cum pump house of JICA Assisted WSS to Pattuvam and Adjoining villages

Project State Plan – 2023-24- Optimisation of production and transmission – Energy Conservation – Supply, Fixing and Commissioning of 845 HP VT pumpset in intake well cum pump house of JICA Assisted WSS to Pattuvam and Adjoining villages
Project Code KNRGOK072314806
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description State Plan – 2023-24- Optimisation of production and transmission – Energy Conservation – Supply, Fixing and Commissioning of 845 HP VT pumpset in intake well cum pump house of JICA Assisted WSS to Pattuvam and Adjoining villages
Status On-going
District Kannur
Executing Office Thaliparambu WS Dn
AS Amount (Rs) 25500000
AS Number PIU1/SP/20/2023-24
TS Amount (Rs)
TS Number
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 State Plan – 2023-24- Optimisation of production and transmission – Energy Conservation – Supply, Fixing and Commissioning of 845 HP VT pumpset in intake well cum pump house of JICA Assisted WSS to Pattuvam and Adjoining villages Irikkur HW Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 May 2024 Submitted for TS approval Thaliparamba WS Dn EE
10 May 2024 Submitted for TS approval Thaliparamba WS Dn EE
09 May 2024 Submitted for TS approval Thaliparamba WS Dn EE
09 May 2024 WORK COMPLETED Thaliparamba WS Dn EE
08 May 2024 Submitted for TS approval Thaliparamba WS Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion 31/12/2023

Processing Dates

AS Date 11 Jul 2023

Other details

Project Officers View