AMRUT-ANTHOOR MUNICIPALITY- AMRUT 2.0-2022-23-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN ANTHOOR MUNICIPALITY

Project AMRUT-ANTHOOR MUNICIPALITY- AMRUT 2.0-2022-23-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN ANTHOOR MUNICIPALITY
Project Code KNRAMRUT112213590P1
Type Package
Main Project AMRUT-ANTHOOR MUNICIPALITY- AMRUT 2.0-2022-23-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN ANTHOOR MUNICIPALITY
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description AMRUT-ANTHOOR MUNICIPALITY- AMRUT 2.0-2022-23-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN ANTHOOR MUNICIPALITY
Status On-going
District Kannur
Executing Office Kalliassery WS Sn
Agreement Number
Agreement Date
TS Amount (Rs) 67600000
TS Number WRD/KWA-CE(NR)/EST_TS/5119/2022_5_1_1
Technical specification Providing 3080 Nos. of FHTCS in the 28 wards of Anthoor Municipality.
Contractor Baburaj.P.k (Mob: 9447152707)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
10 Dec 2023 Pending Pending KRWSA-Organisational Project Risk 1 No comments available. Pending
10 Dec 2023 Pending Pending KRWSA-Organisational Project Risk 1 No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 10/04/2023
Scheduled date of Completion as per agreement 03 Feb 2024
Expected date of Completion 30/04/2025

Processing Dates

TS Date 18 Jan 2023
Estimate Approval 18 Jan 2023
NIT Approval 06 Feb 2023
Tender Closing 20 Feb 2023
Technichal Pre-Qualification 17 Mar 2023
Price bid opening 21 Feb 2023

Approval Dates

Workorder Date 10 Apr 2023
NA 03 May 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kalliassery W S Section - AE
Date: 27/06/2025

Work in progress | 99% Completed

10,000 m distribution pipe laying completed. 3085 FHTCs out of 3085 FHTCs completed.CC VI th and part Bill submitted.

Kalliassery W S Section - AE
Date: 13/05/2025

Work in progress | 99% Completed

10,000 m distribution pipe laying completed. 3085 FHTCs out of 3085 FHTCs completed.CC VI th and part Bill submitted.